 11. Move the winch-rope through the hook. 

 12. Cut the help rope and knot the rope from winch 1 together with winch 2. 

You can secure this knot with glue. Now you can lift the trench cutter. By 

using only one winch, the knot can be positioned into the hook so you 

cannot see it and with both winches, you can now lift the trench cutter 

into an upright position. 

 13. Make sure the hook of the trench cutter is positioned correctly and to 

adjust, just change both ropes on the mast head if necessary. 

 14. The conveying hose starts at the trench cutter on the left side, goes 

through the hook on the frame up to the lower drum on the mast head 

and then down to the Overcarriage drum on the left side (looking from 

behind). You can then assemble the counter weight and clip the short 

end of the conveying hose onto the holder. 

 15. All hydraulic hoses start at the trench cutter right side, through the hook 

on the frame and over the upper drum on the mast head before winding 

onto the right hand drum on the overcarriage. 

 16. On the overcarriage left side, assemble walkway F and ladder G. 

 17. On the overcarriage right side, first assemble the bulkhead plate 

(pre-assembly on F2) into the opening before assembling walkway E 

and ladder G.

  Now the machine is ready for work! For stability, both track frames need 

to be in the extended position.

Anleitung_Bauer_MC96_HDS.indd   7

17.06.16   16:21

Summary of Contents for MC 96

Page 1: ...MC Line MC 96 Seilbagger Anleitung_Bauer_MC96_HDS indd 1 17 06 16 16 21 ...

Page 2: ...MC Line MC 96 Seilbagger Anleitung_Bauer_MC96_HDS indd 1 17 06 16 16 21 ...

Page 3: ...protection 2x I Feder für Rückfallstütze spring for fall back protection 2x J Kolbenstande Rückfallstütze pin for fall back protection 2x K Scheinwerfer Kamera camera flood light 1x L Schloß für Mastabspannung pennant bracket 4x M Hohlniete rivet 2x N Schraube bolt 16x O Mutter nut 16x F1 Fräse mit Hydraulik und trench cutter with water and Waßerschläuchen hydraulic hoses F2 Schlauchaufrollsystem ...

Page 4: ...C A F D E B O P N K Q I M G H L J F5 F1 F2 F3 F4 Anleitung_Bauer_MC96_HDS indd 3 17 06 16 16 21 ...

Page 5: ...nehmba ren Abdeckung auf der linken Seite Ebenso die Öffnungen zum Bedienen der Winden 1 2 und 3 6 Nun ziehen Sie ca 1 5 m Seil von Winde 3 Um das Seil für die Mastver stellung leichter einscheren zu können sollte der A Bock dazu mit einem Klebeband fixiert werden Wie gezeigt wird das Seil von links nach rechts gezogen und geht von der Winde über den A Bock zum Oberwagen Das Seilende wird an einer...

Page 6: ... die Seile in den Rollen am Rollenkopf getauscht werden Nun können die Hydraulikschläuche und der Förderschlauch über die gro ßen Rollen am Auslegerkopf geführt werden 14 Der Förderschlauch wird auf den Anschluß in der linken Trommel gescho ben und aufgewickelt Nun kann das Gegengewicht D montiert werden und der Auslaßhahn in die Halterung eingeklickt werden 15 Die Hydraulikschläuche werden in der...

Page 7: ...o by removing the panel 6 Unwinding about 1 5 m of rope from the small winch pic 5 3 fill the pulley s from left to right and as shown on the picture There is a fixing endpoint on the main body where you can secure the end of the rope To make assembly easier you use a piece of tape to fix the a frame in a static position 7 Add spring I and pin J to the already mounted cylinder 8 To lift the boom t...

Page 8: ...n the frame up to the lower drum on the mast head and then down to the Overcarriage drum on the left side looking from behind You can then assemble the counter weight and clip the short end of the conveying hose onto the holder 15 All hydraulic hoses start at the trench cutter right side through the hook on the frame and over the upper drum on the mast head before winding onto the right hand drum ...

Page 9: ...1 2 3 4 5 C B F3 F5 F4 F5 M H M H F2 1 2 3 Anleitung_Bauer_MC96_HDS indd 8 17 06 16 16 21 ...

Page 10: ...6 7 8 I H J O N L 2 4 3 1 Anleitung_Bauer_MC96_HDS indd 9 17 06 16 16 21 ...

Page 11: ...10 9 13 11 12 Anleitung_Bauer_MC96_HDS indd 10 17 06 16 16 21 ...

Page 12: ...14 15 16 17 D F G E K G Anleitung_Bauer_MC96_HDS indd 11 17 06 16 16 21 ...

Page 13: ...MC Line BAUER Maschinen GmbH BAUER Straße 1 86529 Schrobenhausen Deutschland Tel 49 82 52 97 0 bma bauer de www bauer de bma bauer de Anleitung_Bauer_MC96_HDS indd 12 17 06 16 16 21 ...

Page 14: ...protection 2x I Feder für Rückfallstütze spring for fall back protection 2x J Kolbenstande Rückfallstütze pin for fall back protection 2x K Scheinwerfer Kamera camera flood light 1x L Schloß für Mastabspannung pennant bracket 4x M Hohlniete rivet 2x N Schraube bolt 16x O Mutter nut 16x F1 Fräse mit Hydraulik und trench cutter with water and Waßerschläuchen hydraulic hoses F2 Schlauchaufrollsystem ...

Page 15: ...C A F D E B O P N K Q I M G H L J F5 F1 F2 F3 F4 Anleitung_Bauer_MC96_HDS indd 3 17 06 16 16 21 ...

Page 16: ...nehmba ren Abdeckung auf der linken Seite Ebenso die Öffnungen zum Bedienen der Winden 1 2 und 3 6 Nun ziehen Sie ca 1 5 m Seil von Winde 3 Um das Seil für die Mastver stellung leichter einscheren zu können sollte der A Bock dazu mit einem Klebeband fixiert werden Wie gezeigt wird das Seil von links nach rechts gezogen und geht von der Winde über den A Bock zum Oberwagen Das Seilende wird an einer...

Page 17: ... die Seile in den Rollen am Rollenkopf getauscht werden Nun können die Hydraulikschläuche und der Förderschlauch über die gro ßen Rollen am Auslegerkopf geführt werden 14 Der Förderschlauch wird auf den Anschluß in der linken Trommel gescho ben und aufgewickelt Nun kann das Gegengewicht D montiert werden und der Auslaßhahn in die Halterung eingeklickt werden 15 Die Hydraulikschläuche werden in der...

Page 18: ...o by removing the panel 6 Unwinding about 1 5 m of rope from the small winch pic 5 3 fill the pulley s from left to right and as shown on the picture There is a fixing endpoint on the main body where you can secure the end of the rope To make assembly easier you use a piece of tape to fix the a frame in a static position 7 Add spring I and pin J to the already mounted cylinder 8 To lift the boom t...

Page 19: ...n the frame up to the lower drum on the mast head and then down to the Overcarriage drum on the left side looking from behind You can then assemble the counter weight and clip the short end of the conveying hose onto the holder 15 All hydraulic hoses start at the trench cutter right side through the hook on the frame and over the upper drum on the mast head before winding onto the right hand drum ...

Page 20: ...1 2 3 4 5 C B F3 F5 F4 F5 M H M H F2 1 2 3 Anleitung_Bauer_MC96_HDS indd 8 17 06 16 16 21 ...

Page 21: ...6 7 8 I H J O N L 2 4 3 1 Anleitung_Bauer_MC96_HDS indd 9 17 06 16 16 21 ...

Page 22: ...10 9 13 11 12 Anleitung_Bauer_MC96_HDS indd 10 17 06 16 16 21 ...

Page 23: ...14 15 16 17 D F G E K G Anleitung_Bauer_MC96_HDS indd 11 17 06 16 16 21 ...

Page 24: ...MC Line BAUER Maschinen GmbH BAUER Straße 1 86529 Schrobenhausen Deutschland Tel 49 82 52 97 0 bma bauer de www bauer de bma bauer de Anleitung_Bauer_MC96_HDS indd 12 17 06 16 16 21 ...

Reviews: