7.2.2 WALLMOUNT QUICK TROUBLESHOOTING GUIDE.
Operation
Procedure
ByPassing TCS22 Controller
Disconnect power to the TCS22. Unplug the plug in
connectors J4 and J5 from the controller
Compressor Test
Connect jumper wire on A/C unit low voltage terminals
from R to Y and observe Compressor operation (There
will be a Time delay between the installation of the
jumper and the starting of the Compressor. The
Compressor Time Delay relay will determine the time
delay period.). After the Compressor starts, the jumper
wire can be removed.
Blower Test
Connect a jumper wire on A/C unit low voltage terminals
R to G and observe Blower operation (The Blower will
continue to run for One (1) minute after the jumper is
removed).
Economizer Test
Connect a jumper wire on A/C unit low voltage terminals
R to G and observe Blower operation. After Blower
operation is confirmed, the Economizer can be tested.
Leave the jumper in place from the previous step.
Connect a separate jumper on the A/C unit low voltage
terminals from E to F and observe the Economizer
operation (Never connect power to terminals E or F).
Heater Test
Connect a jumper wire on A/C unit low voltage terminals
R to W1. The Heating contactor will engage when the
jumper is connected. The Blower will also operate while
this jumper is in place. To check the operation of the
Heater, you will have to check the Discharge Air
temperature of the A/C unit.
Restarting TCS22
Remove All jumper wires and reconnect the plug in
connectors J4 and J5 to the controller.
Reapply power to
the TCS22
Summary of Contents for TCS22-***-003
Page 14: ...2100 444 003A Page 8 Figure 1 Front Cover...
Page 15: ...2100 444 003A Page 9 Figure 2 Control Location...
Page 21: ...2100 444 003A Page 15 Figure 4 External Wiring...
Page 22: ...2100 444 003A Page 16 Figure 5 Internal Wiring Figure 6 Power...
Page 23: ...2100 444 003A Page 17 Backup System...