INSTALLATION
1.
Do an excavation for the foundation plate, fix the anchors
to the plate by the furnished screws. (Fig 3).
NOTE: fix the plate to the concrete, keeping attention to
position at 65 mm from the gate (Fig 4).
2.
Place flexible pipes necessary for the passage of electrical
connection cables. Flexible pipes should exceed at least 3
cm from the hole on the plate. (fig 3).
3.
Cement in perfect plane the plate.
4.
Wait till the cement has dried up.
5.
Place the cables for the connection between accessories
and electrical feeding. (fig 2).
6.
Fix the motor on the foundation plate by his screws.
Pass throw the hole on the plate the cables for the electrical
connection.
Fig. 3
Fig. 5
Fig. 4
FIXING OF THE RAK
1.
Set the rack with screws TE 8 x 25 and spacing bars.
NOTE: it is suggestible to close the screws of the rack in
the upper part of the buttonhole. This position allows to
adjust the rack when the motor, in the time, will lower.
2.
Unlock the motor.
3.
Move manually the leaf in an opening position.
4.
Place the rack over the pinion in correspondence of the
first spacing bar.
5.
Fix the rack element to the leaf with a clip.
6.
Manually move the leaf in closing till the third spacing bar
of the rack and sold it.
7.
Sold definitively the 3 spacing bars on the gate.
8.
Bring near another rack element to last fixed, using a piece
of rack if 150mm, in order to put in phase the 2 elements.
9.
Manually move the leaf in closing till reaching the
correspondence with the pinion.
NOTE: Check that all the elements of the rack works with the
centre of the tooth’s of the pinion.
10. Sold the 3 spacing bars of the element. los tres
distanciadores del elemento.
11. In order to obtain the right slack between rack and pinon,
lower the gear of 1.5mm moving the screws of the
foundation plate. At the end of such regulation, close the
fixing screws.
Manually check that the gate is free to completely open and that the
movement of the leaf is regular and without frictions
INSTALLATION OF LIMIT SWITCHES