583 M1 01 F
24-11-2009
1. PACKING DETAILS
Each standard equipment includes,
- 1 guiding tube, diameter 63 mm
- 1 red PVC counterweight Ø 50 with a built in magnet
- 2 stainless steel cable clamps
(only with stainless steel version)
- 5 m long cable (PPH, stainless steel, PVC coated...)
(it could be different within your specifications)
- 1 PPH float Ø 98, or 1 stainless steel float
(Ø 100 mm or Ø 200 mm)
- 1 pulley "upper end guiding tube"
- 1 pulley "over tank"
2. MOUNTING
1/
First, install the collars on the tank.
2/
Fix the pulley "over tank"
3/
Install the tube.
4/
Evaluate the necessary cable length
It could be easier now, to pass the cable through the
transfer tubes,
than later on
(depending of total length)
5/
Fit the float with the cable
- Stainless steel float with one stainless steel clamp
(see picture B)
- PPH: cable is attached doing a knot after it passed
through the connection to be screwed
6/
Install the float inside the tank
Pass the cable inside the pulleys and fix it to the
counter weight
(see picture C)
.
7/
Let the counterweight suspended to the cable and fix
a screw the pulley "upper end guiding tube".
8/
Caution: be sure the cable is correctly set on the
pulley wheels.
Reminder: When the tank is empty,
the counter weight is in the upper part
of the guiding tube.
3. MAINTENANCE
This kind of level indicator does not require any specific
maintenance.
Pic. B
Pic. C