FXV3/CXVT Rigging & Assembly Instructions
–
Introduction
Page | 9
Cold Weather Operation
These products must be protected by mechanical and operational methods against damage and/or reduced effectiveness
due to possible freeze-up. Refer to the FXV and FXV3 Closed Circuit Cooling Tower CXVB and CXVT Evaporative
Condenser Operation & Maintenance Manual at
or contact your local BAC Representative for
recommended protection alternatives.
Placement
All evaporative cooling equipment must be placed in a location that ensures an adequate supply of fresh air into the air intakes.
When units are located adjacent to walls or in enclosures, care must be taken to ensure the warm, saturated, discharge air is
not redirected back to the air intakes. Each unit must be positioned to prevent the introduction of discharge air into the
ventilation systems of the building on which the unit is located and of adjacent buildings. For detailed recommendations on BAC
equipment layout, see our website at
or contact your local BAC Representative.
NOTICE:
Each unit must be located and positioned to prevent the introduction of discharge air into the
ventilation systems of the building on which the unit is located and of adjacent buildings.
Warranties
Please refer to the Limitation of Warranties (located in the submittal package) applicable to and in effect at the time of the sale/
purchase of these products.
Unit Operation
Prior to start-up and unit operation, refer to the unit operation & maintenance manual shipped with the unit and also available
at