Commissioning Menu
Figure 10: Commissioning Menu
1.
Commission and Gas Control Start / Stop Button
–
Press to start the 20 minute commission
cycle. Once complete the workstation will enter gas control mode and will inject Hydrogen
when low pressure is detected.
2.
Forced Demand
–
Press to toggle forced demand option on or off. When forced demand is
on a 2 second shot of Hydrogen will be injected every 20 minutes regardless of workstation
low pressure.
3.
Commission Bypass
–
The button will appear after the gas control button has been
pressed. The commission bypass will stop the 20 minute commission from completing and
will
automatically put the workstation into gas control mode.