background image

Masoneilan 49000 Series Energy Management Control Valves  |  3

Copyright 2020 Baker Hughes Company. All rights reserved.

Installation

Piping Cleanliness 

Before installing the valve in the line, clean piping and valve of all 

foreign material such as welding chips, scale, oil, grease or dirt. 

Gasket mating surfaces must be thoroughly cleaned to ensure 

leak-free joints. Sacrificial start-up fixtures can be purchased from 

Baker Hughes to protect the operational trim during the installa-

tion and line flushing phases.

CAUTION

CAUTION

WARNING

DANGER

If major system or piping modifications (or repairs) are 

performed, thorough flushing and blowdown of the 

system will be required prior to reinstalling the trim. 

Sacrificial flushing trim should be installed in the valve 

to protect the integrity of the flow passages. Failure to 

follow this warning will violate the valve warranty agree-

ment and could result in control instability, excessive 

noise levels, and valve leakage.

Isolation Bypass Valve

To  allow  for  in-line  inspection,  maintenance  and  removal  of  the 

valve without service interruption, provide a manually operated 

shutoff valve on each side of the control valve and a manually 

operated throttling valve in the bypass line.

Heat Insulation 

In case of a heat-insulated installation, do not insulate the valve 

bonnet and take protective measures relative to personal safety.

Hydrostatic Testing and Line Cleaning

During this operation, the control valve must not be used as an 

isolating valve. This means that the valve must always be opened 

before  carrying  out  pressure  tests  in  the  process  line,  cleaning 

of pipes, etc. otherwise equipment damage or failure of the seal 

rings could result. If the valve is to remain installed during line 

cleaning,  flushing  trim  MUST  be  installed  to  prevent  damage  to  

trim components.

Flow Direction

The  valve  must  be  installed  so  that  the  process  fluid  will  flow 

through  the  valve  in  the  direction  indicated  by  the  flow  arrow 

located on the body.

Welded Connections

CAUTION

CAUTION

WARNING

DANGER

Carefully review the information in this section prior to 

welding any valves inline. Refer any additional ques-

tions to the local Baker Hughes Sales Office or Service 

Center.

Pre-Weld Preparation

Carefully follow the installation steps defined in the sections noted 

above prior to performing weld procedures.

Welding Process

Perform  welding  process  in  accordance  with  the  standard 

requirements for the materials and weld construction of the specific 

valve. Apply post weld heat treatment if required.

CAUTION

CAUTION

WARNING

DANGER

Internal valve components should be removed prior 

to performing welding or pre/post weld heat treatment 

weld heat treatment in order to prevent damaging any 

soft goods (such as PTFE seals). If unable to remove 

the elastomeric components, then other methods must 

be employed to prevent the local temperature around 

the seals from exceeding the maximum material limits 

(typically 450°F / 232°C for PTFE based materials).

Post Weld Cleaning & Assembly

Inspect the body, bonnet, and trim components for cleanliness and 

surface condition. Remove any foreign materials, such as weld 

chips, slag or scale. Make sure there are no nicks, scratches, burrs 

or sharp corners on sealing and sliding surfaces. Clean all gasket 

interface surfaces and reassemble using new gaskets to ensure 

sealing integrity.

Actuator Assembly

Assemble the pneumatic actuator onto the control valve using the 

appropriate instructions for the specific actuator model and type. 

Connect air pressure lines to the actuator ports to meet intended 

operating mode (i.e., air-to-extend, air-to-retract, or double-acting).

Disassembly

CAUTION

CAUTION

WARNING

DANGER

Prior to performing any maintenance on the valve, iso-

late the valve and vent the process pressure.

Valve Actuation

Access to the internal components of the valve should be 

accomplished with the actuator removed. Follow the detailed 

instructions below and refer to the appropriate actuator 

instruction manuals.

CAUTION

CAUTION

WARNING

DANGER

Actuator may be pre-loaded with tension from air pres-

sure or springs. Prior to disconnecting instrumentation 

read all instructions for the specific actuator.

Disconnect Instrumentation

Disconnect all mechanical connections between the positioner and 

the other instruments. Disassemble the valve stem and actuator 

stem coupling as described in the following sections.

Summary of Contents for Masoneilan 49000 Series

Page 1: ...Masoneilan 49000 Series Energy Management Control Valve Instruction Manual Rev D Baker Hughes Data Classification Public ...

Page 2: ...ICULAR REQUIREMENTS FOR OPERATION OF OTHER EQUIPMENT AT THE SITE THESE INSTRUCTIONS DO NOT PURPORT TO COVER ALL DETAILS OR VARIATIONS IN EQUIPMENT NOR TO PROVIDE FOR EVERY POSSIBLE CONTINGENCY TO BE MET IN CONNECTION WITH INSTALLATION OPERATION OR MAINTENANCE SHOULD FURTHER INFORMATION BE DESIRED OR SHOULD PARTICULAR PROBLEMS ARISE WHICH ARE NOT COVERED SUFFICIENTLY FOR THE CUSTOMER OPERATOR S PUR...

Page 3: ...uator and Accessories 2 Numbering System 2 Unpacking 2 Installation 3 Piping Cleanliness 3 Isolation Bypass Valve 3 Heat Insulation 3 Hydrostatic Testing and Line Cleaning 3 Flow Direction 3 Welded Connections 3 Pre Weld Preparation 3 Welding Process 3 Post Weld Cleaning Assembly 3 Actuator Assembly 3 Disassembly 3 Valve Actuation 3 Disconnect Instrumentation 3 Air to Retract Actuators 4 Threaded ...

Page 4: ...gs 6 Metal Seal 6 Valve Plug 6 Valve Reassembly 6 Pinning the Valve Plug 6 Completing Valve Body Assembly 6 Seat Ring Installation 6 Trim Bonnet and Body Assembly 7 Balance Seal Installation B019 7 Flow to open installation FTO 7 Flow to close installation FTC 7 Balance seal metal high temp type FTO and FTC seal is non directional 7 Bonnet Assembly 7 Tightening Body Nuts 7 Packing Box Assembly 8 A...

Page 5: ...prior notice The information contained in this manual in whole or part shall not be transcribed or copied without Baker Hughes s written permission Please report any errors or questions about the information in this manual to your local supplier These instructions are written specifically for the 49000 Series control valve and do not apply for other valves outside of this product line Useful Life ...

Page 6: ...ves or Masoneilan Parts Department When ordering spare parts the MODEL AND SERIAL NUMBERS indicated on the manufacturer s serial plate MUST BE GIVEN The serial plate is on the side of the actuator yoke Actuator and Accessories Actuators and other valve accessories have their own instruction manuals that provide information and details on the assembly and installation Refer to the appropriate instr...

Page 7: ...welding any valves inline Refer any additional ques tions to the local Baker Hughes Sales Office or Service Center Pre Weld Preparation Carefully follow the installation steps defined in the sections noted above prior to performing weld procedures Welding Process Perform welding process in accordance with the standard requirements for the materials and weld construction of the specific valve Apply...

Page 8: ...r valve configurations designed with a two piece bonnet assembly bonnet and bonnet flange 5 Disassemble the bonnet flange 3 from the valve body 1 6 Lift the bonnet 2 and metal seal 11 to remove from the valve body 1 During this operation the valve stem 8 must be pushed downward to ensure the valve plug 6 remains inside the valve body Note The metal seal 11 will require some force to remove from th...

Page 9: ...ary to separate the valve plug stem from the actuator stem 1 Remove the packing flange nuts 19 from the packing flange studs 18 2 Lift the packing flange 17 and packing follower 16 up along the valve stem 8 3 By means of a puller remove the packing 15 being careful not to damage the sealing surface of the packing box or the valve plug stem 4 Replace the packing 15 Press a back up ring carbon graph...

Page 10: ...ly impair the mechanical strength and integrity of the valve plug stem assembly Completing Valve Body Assembly Proceeds as follows Seat Ring Installation 1 After checking all sealing surfaces to ensure they are thoroughly clean assemble the seat ring gasket 10B in the valve body 1 Make sure the gasket is centered properly in the body This gasket or similar part can be kept after lapping for future...

Page 11: ...the two backup rings over plug and seat against the Omni seal as illustrated See Figure 5b Balance seal metal high temp type FTO and FTC seal is non directional 1 Ensure that the plug and the seal groove are clean and free of sharp edges 2 Lightly lubricate the seal inner and outer rings top of plug and seal groove with Dow Corning 111 or equivalent 3 Slide the rings over plug and seat in the groo...

Page 12: ...nnet flange are tightened down evenly to ensure proper alignment and fit of the internal components required for smooth valve operation and performance In larger sizes 12 and larger it is highly recommended that two assembly personnel directly opposed to one another perform the torque sequence and assure even installation i e no tipping or uneven gaps between the bonnet flange and body At each tor...

Page 13: ... 1 375 8 UN 2A 8 400139447 136 0 5 35 89 103 660 760 1500 1 875 8 UN 2A 8 365637000 202 0 7 95 260 300 1900 2200 2500 2 250 8 UN 2A 8 400148235 263 3 10 37 490 560 3600 4100 8 600 1 375 8 UN 2A 12 720016107 151 0 5 94 84 96 620 710 1500 1 875 8 UN 2A 12 001247622 221 1 8 70 260 300 1900 2200 2500 2 250 8 UN 2A 12 720015679 288 3 11 35 470 540 3500 4000 10 600 1 625 8 UN 2A 12 720017027 194 0 7 64 ...

Page 14: ...10 Baker Hughes Copyright 2020 Baker Hughes Company All rights reserved Figure 8 Typical Assembly ...

Page 15: ...and figure 11b for stem connector positioning 3 Pneumatically or with the handwheel stroke the actuator to the rated spring range or stroke if using the handwheel 4 Using the stem lock nuts 1 unscrew the plug stem until the plug touches the seat CAUTION CAUTION WARNING DANGER DO NOT TURN the plug against the seat as damage to parts can occur 5 Release the pressure in the actuator or back off the h...

Page 16: ...5 7 16 2 5 63 5 9 50 241 3 23 0 8 20 8 25 209 5 23 1 5 38 8 62 218 9 23 2 0 51 9 12 231 6 23 2 5 63 5 9 59 243 6 Table 3 Position of Top Stem Connector Parts Reference For Spring Diaphragm Actuators Type 87 88 Multispring Item No Description 1 Hex Nut 2 Stem Connector Bottom 3 Cap Screw Hex Head 4 Stem Connector Top 5 Cap Screw Socket Head 6 Connector Insert 7 Pointer 8 Screw Pan Head 9 Scale Trav...

Page 17: ...ol Valves 13 Copyright 2020 Baker Hughes Company All rights reserved Figure 10b Type 88 Actuator Air to Retract Open Figure 9b Type 87 Actuator Air to Extend Close Figure 9a Type 87 Air to Close No 10 16 23 Figure 10a Type 88 Air to Open No 10 16 23 ...

Page 18: ... pressure through the manual loading panel to completely extend the actuator stem 4 Retract the actuator stem either pneumatically or with a handwheel approximately 1 2mm using the visual stroke scale as shown in Figure 11 5 Assemble the Split Clamp 22 Note If the split clamp does not engage with both stems then retract the actuator stem until alignment and engagement is achieved CAUTION CAUTION W...

Page 19: ...ement Control Valves 15 Copyright 2020 Baker Hughes Company All rights reserved Figure 14 Model 52 air to extend without handwheel Figure 13 Model 51 Double Acting Without volume chamber Figure 15 Model 53 air to retract without handwheel ...

Page 20: ...ecessed head screw 5 Hexagon socket head cap screw 28 Exhaust pipe 6 Spring lock washer 29 Spring lock washer 7 Spring tube 30 Plug 8 Guide bushing 31 Piston S A 9 Compression bolt 32 Guide bushing 10 Upper spring but ton 33 O ring Piston rod 11 Thrust bearing 34 Rod scraper 12 Compression nut 13 Separator plate Model 52 53 14 Cylinder tube Cylinder tube 15 Guide ring 16 Guide ring 17 Top plate 18...

Page 21: ...Masoneilan 49000 Series Energy Management Control Valves 17 Copyright 2020 Baker Hughes Company All rights reserved Notes ...

Page 22: ...18 Baker Hughes Copyright 2020 Baker Hughes Company All rights reserved Notes ...

Page 23: ...Masoneilan 49000 Series Energy Management Control Valves 19 Copyright 2020 Baker Hughes Company All rights reserved Notes ...

Page 24: ...Baker Hughes Company Other company names and product names used in this document are the registered trademarks or trademarks of their respective owners BHMN 49000 IOM 31222D 0121 01 2021 Tech Field Support Warranty Phone 1 866 827 5378 valvesupport bakerhughes com Direct Sales Office Locations Australia Brisbane Phone 61 7 3001 4319 Perth Phone 61 8 6595 7018 Melbourne Phone 61 3 8807 6002 Brazil ...

Reviews: