Nova846 Outdoor 8x5W Two-Carrier TDD eNodeB Installation Guide
37
Figure 3-21: Carrier Setting
3.8.8 Reboot
Once the basic configuration settings are saved, reboot the eNB. Go to the
Reboot
menu and click
Reboot.
Confirm intent to reboot by clicking
OK
at the message prompt (Figure 3-22).
Figure 3-22: Reboot
3.8.9 Verify eNB Operational Status
When the eNB is finished rebooting, check the eNB status using the eNB GUI and the OMC. Once
the eNB is mounted at its intended destination and powered on, recheck the status settings.
•
eNB
GUI
: Go to
BTS Info > Basic Info
and check the
Cell Status
field (Figure 3-23). It should
show
Active
. Also, check that
GPS Sync Status
is reported as
Synchronizing
.
•
OMC:
Go to
eNB > Monitor
to see if the
Cell Status
shows
Active
and the
Sync Status
shows
GPS Synchronized