Aurora243 Outdoor 2x10W TDD gNodeB Installation Guide
37
4.1.7 Verify gNB Operational Status
After the gNB reboots, check the gNB status using the gNB GUI. Once the gNB is mounted at its intended
destination and powered on, recheck the status settings.
•
gNB GUI
: Go to
Basic Setting > Basic Info
(Figure 4-11) and check if the
Cell Status
and
NG Status
field shows
Active
. Also, check that
GPS Sync
Status
is reported as
Synchronized
.
Figure 4-11: Verify Operational Status
Before commercial deployment, Baicells recommends implementing cell site acceptance testing of a new
site to ensure the service meets expectations, document network speeds at various cell locations, and
verify RF coverage.