Chapter 3. Eclipse Edge Installation
Installation Process for Edge
This section provides a basic guide, in order, of an Eclipse Edge hardware installation
process. Installation can be completed up to antenna alignment without the use of
Eclipse Edge Portal, the PC based craft tool. Portal is required to check and configure
an Eclipse Edge terminal / link.
Hardware installation typically proceeds as follows:
1. Pre-Installation
• Unpack equipment
• Verify system configuration:
• Check basic components
• Check kits and accessories
2. Installation
• Antenna
• ODU
• ODU grounding
• ODU cable (running and fastening)
• Cable grounding and weatherproofing
• Lightning surge suppressor
• Traffic and NMS cables
3. Install Eclipse Portal
4. Antenna Alignment
• Power On
• Connect PC and log onto Portal
• Configure equipment
• Align antenna/s
• RSSI at the ODU or RSL indication in Portal
Eclipse Edge Installation Prerequisites
You must obtain the tools and materials, and review the procedures, before going on
site to install Eclipse Edge. This section includes:
• Tools and Materials for Edge Installation
• Unpacking Edge Installation Equipment
Tools and Materials for Edge Installation
Ensure you have all necessary tools and material before going to site.
lists the tools and material that must be sourced or supplied by the
installer.
Summary of Contents for ECLIPSE EDGE
Page 1: ...ECLIPSE EDGE Version 5 USER MANUAL 260 668080 001...
Page 2: ......
Page 3: ...Eclipse Edge Microwave Radio System User Manual Software Version 5 0 March 2013...
Page 14: ...16 Aviat Networks INDEX...
Page 18: ......
Page 26: ...8 Aviat Networks Chapter 1 Health and Safety...
Page 272: ...36 Aviat Networks Chapter 3 Eclipse Edge Installation...
Page 273: ......