Chapter 2

 

 INSTALLATION 

 

Before proceeding to the installation of the turnstile, unpack all components and check 

to make sure the all parts from the packing slip are included, verify dimensions and conduit runs. 

Use the turnstile template to properly align and lay out the site and to determine the right 

location of the floor stub-ups and anchors. 

Site preparation: 

-

 

Make sure that the floor is level before the installation process starts. 

-

 

When measuring the distance between the cabinets always refer to the center of 
the cabinets, not the corners. 

-

 

Using the factory provided template and design layout drawings outline the exact 
position  of  each  turnstile.  Make  sure  the  floor  outline  includes  the  space 
dedicated to conduit stub-ups. 

-

 

Install  conduits  for  low  voltage  cables  and  for  110Vac  (220Vac)  power.  Size 
conduits based on the number of cables and follow local installation codes. 

-

 

Install one ¾ inch conduit for turnstile communication between two cabinets that 
form one lane. 

-

 

Depending on the position, each enclosure can host one or two motors. The end 
cabinets  have  only  one  motor  (SM  series)  and  the  middle  cabinets  have  two 
motors (DM series).  

-

 

Each controller operates one motor. SM series have one controller and DM series 
have two controllers. 

-

 

On the turnstile floor footprint, locate anchoring holes. Drill and install foundation 
screw bolts or M12 anchor bolts. 

-

 

Align and install the turnstile cabinet on the anchor bolts. Secure the cabinet to 
the bolts. 

-

 

Follow wiring diagram to terminate the cables on the turnstile control panel. The 
following connections are required: 

o

 

Card reader to control panel reader port. The control panel can be located 
inside the turnstile or outside. 

o

 

Communication cable between cabinets. 

o

 

Lane OPEN command from the turnstile to the access control panel door 
open relay. 

o

 

If  required,  an  emergency  open  button  or  switch  can  be  wired  to  the 
turnstile controller board. 

o

 

110Vac (220Vac) is required for each turnstile cabinet. 

 
 
 
 

Summary of Contents for TS-FBS01

Page 1: ...INSTALLATION MANUAL FOR TS FBS01 FLAP BARRIER TURNSTILES Revision Date Description Initials 0 2017 07 02 New template LR 1 2018 05 12 Manual update KN ...

Page 2: ...Page 2 of 8 Index Chapter 1 INTRODUCTION 3 1 1 Product features 3 1 2 Product specifications 3 1 3 Product dimensions 4 Chapter 2 INSTALLATION 7 Chapter 3 TROUBLESHOOTING AND SUPPORT 8 ...

Page 3: ... Customized flap etching and color reader cut out or barcode reader insert 1 2 Product specifications The TS FBS01 flap barrier turnstiles have the following characteristics Power requirements 110Vac 220Vac 250W to 500W The flap barrier turnstiles are provided with different power supplies based on country and customer s requirements Check the product label before connecting to any power supply Dr...

Page 4: ...Page 4 of 8 1 3 Product dimensions Top View Single Movement Front View Single Movement ...

Page 5: ...Page 5 of 8 Top View Double Movement Front View Double Movement ...

Page 6: ...Page 6 of 8 Side View Two Lane Layout ...

Page 7: ...ation codes Install one inch conduit for turnstile communication between two cabinets that form one lane Depending on the position each enclosure can host one or two motors The end cabinets have only one motor SM series and the middle cabinets have two motors DM series Each controller operates one motor SM series have one controller and DM series have two controllers On the turnstile floor footpri...

Page 8: ...g Installation Design Chapter 3 TROUBLESHOOTING AND SUPPORT For Troubleshooting and Support please contact Aventura Technologies Inc Tel 1 631 300 4000 Fax 1 631 434 7000 Email techsupport aventurasecurity com Skype aventurasupport Website http www aventurasecurity com ...