Page 22 - Installation
Page 22
DECT - Installation Manual
Installing DECT Base Stations (DBS)
38HBKD0001SAH – Issue 14 (27th October 2003)
Mounting the Base Station
Each Base Station is supplied with 1.5mtrs of cable for connection to the
slave jack socket (see page 3).
To mount a Base Station, perform the following:
1. Check the proposed position of the Base Station and ensure that there
is a minimum of 200mm's clearance on all sides of the Base Station.
2. Use the Base Station Wall Mounting Bracket (see figure below) as a
template to mark the required holes.
Ensure that the Base Station is
level. Drill and insert the wall fixings for the No. 6 round-head screws.
3. Run the Base Station line cord through the access hole before fixing
the bracket to the wall with the two No. 6 round head screws.
4. Push the Base Station line cord into it's socket on the Base Station.
5. Slide the Base Station onto the mounting bracket (a firm push is
required to slide the Base Station lugs over the pins on the wall
mounting bracket).
Wall mounting
securing screw slots
Base Station line
cord entry point
Top – viewed from front
6. Connect the base station line cord from the base station to the slave
jack socket provided for the base station.
Note:
For country variants, use the following table:
Socket Type
Pins
LJU 2/3A
RJ45
RJ11
3 & 4
4 & 5
3 & 4
7. Connect, using twisted pairs cable, the slave jack socket to the MDF
(see pages 19 and 20 for MDF wiring).
Configuring the Base Stations
For the system to function correctly, it must measure the cable delay on
signals to and from each Base Station. Whilst this process is being
performed the system cannot handle calls (