Chapter 1
Installing the Application Gateway
Rack Mounting the Application Gateway
8
Application Gateway Hardware Installation Guide
Connecting the Rack Rails to the Rack
Determine where you want to place the server in the rack. Position the
fixed rack rail/sliding rail guide assemblies (B) at the desired location in
the rack, keeping the sliding rail guide facing the inside of the rack. Screw
the assembly securely to the rack using the brackets provided. Attach the
other assembly to the other side of the rack, making sure that both are at
the same height and have the rail guides facing inward.
Installing the Server into a Four-Post Rack
You should now have rails attached to both the server and the rack unit.
The next step is to install the server into the rack.
To install the server into a four-post rack:
1
Line up the rear of the chassis rails with the front of the rack rails.