INSTALLATION-MANUAL
Scissor
ASG-3005
ASG-4005
ISSUED 11-02-04
AUTEC Hefbruggen bv
storage locations of paint and wax, and
also rooms where there is a danger of
explosion.
ELECTRICAL POWER SUPPLY
POINT.
The client must ensure that there is a
power supply point near the installation
site, which satisfies all the applicable
legal requirements (see page 4). If such
power supply is not available, the
installation technician will arrange for
an emergency cable. The lift shall be
tested after the emergency power
supply has been dismantled. The client
must then arrange for a duly qualified
and recognised installation technician to
lay the final wiring.
IMPORTANT INSTALLATION
MEASURES
The lift must be installed taking into
account the dimensions of other objects
(Fig. 4), and the rules and regulations
applicable in the country where the lift is
installed.
In particular, attention should be paid to
the following :
The minimum height from the floor,
at the installation location, must be
5000 mm
The minimum distance from the
walls must be 1 m.
The minimum working area is 500
mm
Industrieterrein IJsselveld, Vlasakker 11, 3417 XT MONTFOORT, The Netherlands
Tel: +31 348 477000 Fax: +31 348 475104 Internet: www.autec.nl - E-mail: [email protected]
en/TD-ASG-4005-3
Adequate room for working
Adequate room for maintenance,
access-/ and exit routes.
Position with respect to other
machines
In the neighbourhood of the power
supply point to ensure problem-free
connection.
Fig.
4
LIGHTING
All the parts of the lifting lift must be
uniformly and adequately lighted.
D
uring the installation work,
there must be no unauthorised
persons in the safety zone around
the lift (Fig. 4).
INSTALLATION OF THE LIFT
Take the two parts of the lift out of the
packing case. Seal the hydraulic hoses
openings with tape in order to prevent
the contamination of the hoses. To
move the vehicle loading tracks, one
must use a lifting vehicle having
sufficient lifting capacity. Lower the lift
onto the desired installation location.
Fig. 5
Lift the lifting tracks with the help of a
crane to a height of around 800 mm and
place the lift in its interlock.
Fig.
6
CONNECTING THE HYDRAULIC
SYSTEM (see figure 20)
Put the control cabinet in the selected
spot. Please keep in mind the minimum
distance to be maintained with respect
to other objects. Open the control
cabinet with the help of a socket
wrench. The connections to the
connecting block (Fig. 7) in the control
panel, and the hydraulic system hoses
are marked. Connect the hydraulic
hoses according to the following
drawing. Thereafter firmly tighten the
connections.
Fig. 7
Ref.A
Fig. 8
6. CONNECTING TO THE
MAINS
WARNING
The following actions must only be
carried out by duly authorised
personnel :
First check the following points before
connecting to the mains: