Completion of Work
Before commissioning, check all fastening screws, electrical, pneumatic and hydraulic
lines and, if necessary, tighten these. Warning: in some cases, this must be checked at
regular intervals and tightened if necessary (note in the instructions).
Checking and adjusting limit switches
If the limit switches do not work or are working incorrectly,
they can be adjusted as described below.
Adjusting the TOP (
1
) limit switch
Raise the lift to
1800 mm.
The switch can be installed at two positions. Install it in the correct
position for operating the switch when the lifting carriage is lifted to the
desired height. Tighten the screws after adjusting
.
Adjusting the CE STOP (
2
) limit switch
Move the lift to a height of 220 mm. The switch can be installed at two
positions. Install it in the correct position for operating the switch when
the lifting carriage is lowered to the desired height. Tighten the screws
after adjusting
.
Adjusting the SAFETY CHAIN (
3
) limit switch
This switch must be installed correctly according to the following instructions
to ensure the switch can be operated by the switch cam (
4
) and prevent the lift dropping if the chains
slacken or snap.
Change the position of the switch or move the switch lever on the limit switch
up or down a little until the optimal switching position has been reached.
Tighten all screws after adjusting.
1
2
3
4
Summary of Contents for Single Lift 35M
Page 3: ...BEDIENUNGSANLEITUNG ATH Single Lift 35M ...
Page 51: ...OPERATING INSTRUCTIONS ATH Single Lift 35M ...
Page 99: ...MANUEL D UTILISATION ATH Single Lift 35M ...
Page 147: ...NÁVOD K OBSLUZE ATH Single Lift 35M ...
Page 195: ...MANUAL DE INSTRUCCIONES ATH Single Lift 35M ...
Page 243: ...BEDIENINGSHANDLEIDING ATH Single Lift 35M ...
Page 291: ...INSTRUKCJA OBŁSUGI ATH Single Lift 35M ...