background image

35

36

6.2.4 Historical information

Clicking  “historical  information”  can  enter  into  the  sub-menu  of  the  "historical 
information".
History of failure: all the common history of failure details can be found by flipping 
the page up and down.

The common fault information, see table 6.3.1.

6.2.5 Operation data

Clicking  the  “Operation  data”  in  any  interface  will  enter  into  the  submenu  of 
“operation data”.

The  sub-menu  includes:  real-time  data,  the  power  curve,  and  energy  yield  figure. 
Pressing  the  left  button  can  enter  into  the  corresponding  sub  menu  interface.  The 
default interface is the real-time data interface.

Insert USB Disk on the back of the LCD display, and the real time operation data will 
be  stored  in  the  USB  Disk  in  every  minute.  Inverter  will  create  a  “CSV”  format  file 
every month in the USB disk for data storage.

Real-time  data:  current  DC  power  generation  parameters  and  real-time  data 
including the grid voltage, the grid frequency, the grid current, DC input voltage, DC 
input  current,  the  internal  temperature  of  the  chassis  as  well  as  the  total  power 
generation time (updated in real time). When total power is more than 100,000kW, it 
will  be  measured  by  MK;  when  total  power  is  less  than  100,000kW,  it  will  be 
measured by kW. 

Summary of Contents for PCS100

Page 1: ... User Manual GR UM 053 A 01 Shenzhen ATESS Power Technology Co Ltd 86 755 2998 8492 www atesspower com T W 1st Floor of Building 3 at Sector B and 3rd Floor of Building 9 Henglong Industrial Park No 4 Industrial Zone Shuitian 86 755 2998 5623 F ...

Page 2: ...3 7 Storage 3 8 Dimension 3 9 Packaging information GUI instruction 6 Pilot operation 5 2 Inspection 5 4 Pilot operation completion 5 3 Power on steps 5 1 Relevant requirements 5 5 5 Power off steps 6 1 LCD display screen introduction 6 2 LCD operation 6 3 LCD display information schedule Routine maintenance 7 7 1 Replacing the dust screen 7 2 Regular maintenance Products installation 4 4 2 Tools ...

Page 3: ... professional electricians or professionally qualified personnel can transport or install this product 2 The operator should be fully familiar with the structure and working principle of the entire Energy Storage system 3 The operator should be fully familiar with this manual 4 The operator should be fully familiar with the local standards of the project Qualification 1 3 How to use this Manual Re...

Page 4: ...for qualified electrical technician only When inverter operating don t touch any electrical parts except for the touch screen All electrical operation must comply with local electrical operation standards Warranty service for the inverter does not contain module maintenance Permission from the local utility company is required before installing the Energy Storage system and only professional perso...

Page 5: ...ast 5 minutes Only professional technical personnel are qualified for the operation Maintenance and modification Only personnel with ATESS authorization are qualified for the maintenance and modification And to ensure personal safety use original accessories provided by the manufacturer only Otherwise electrical safety and EMC might not comply with the required standard Function and safety paramet...

Page 6: ...lation tools or other unnecessary items are not left inside the inverter before starting up Item 4 Maintenance notice Maintenance can only be carried out after the inverter totally discharged Product description 3 ATESS PCS100 bidirectional battery inverter is designed for energy storage system it converts DC current generated by battery bank into AC current and feed it into the load grid also it ...

Page 7: ...event dust from entering into the inverter Figure 3 3 1 Part description There are two LED indicators on the inverter which is used to display the current status of the inverter Figure 3 3 1 2 LED indicators LED Description POWER The indicator lights when power supply to the inverter is normal FAULT The indicator lights when power supply to the inverter is normal Figure 3 3 2 LED status Indicator ...

Page 8: ... eliminated 3 4 4 Permanent fault mode When the DC power system is in serious failure the inverter will immediately disconnect the AC contactor and enters into the Permanent fault mode so as to ensure the safety of the system For example inverter module failure etc please contact your local dealer or ATESS directly when inverter enters permanent fault mode repairmen on site is not allowed without ...

Page 9: ...perature range 40 55 Storage relative humidity range 5 95 Operating temperature range 25 55 Operating relative humidity range 5 95 Max altitude 2000 m 3 6 Protection Anti islanding When the local power grid shutdown due to malfunction or maintenance of equipment the inverter will be physically cut off the connection to the grid in order to protect operating personnel working in the electricity gri...

Page 10: ...et and bottom outlet Cable trenches are recommended The cable trenches are often designed and constructed by the construction side based on relevant standards with the equipment weight and dimensions required to be considered Good electrical connection is needed between different cable trenches and GND terminals Wiring specification Cables in the inverter can be classified into either power cables...

Page 11: ...pare parts required for whole machine installation Tools and spare parts required for installation is as follows Hoisting crane forklift or fork lift truck with the capacity for bearing the weight of the inverter Torque wrench Screwdriver Wire stripper Terminal crimping machine Heat dryer Megger and multimeter Before the inverter is moved to the designated place we suggest to lay the DC input cabl...

Page 12: ...inet of the equipment according to the following procedures Procedure 1 Demolish the wood side and roof of the packaged cabinet Procedure 2 Demolish the out set package material on the machine Procedure 3 Demolish the fastening screws between the machine and the pallet Demolish the front and back cover lids of the pedestal Screw off the hold down nuts at the bottom of the wood pallet Remove the sc...

Page 13: ...ils and the grid is three phase grid Meanwhile it shall be permitted by local power supply department before install Grid connected inverted power Model ATESS PCS100 Grid Voltage Limit Grid Frequency Limit 360Vac 440Vac 45Hz 55Hz 55Hz 65Hz Cable Cu Cable Diameter Requirements mm Model ATESS PCS100 3 Cable requirements Aperture DC Φ10 30N m DC Grid Phase A 2 1 input cables with each at least 70 mm ...

Page 14: ...sitive and negative with a multimeter 3 Connect the positive of the battery to the DC of DC input 4 Connect the negative of the battery to the DC of DC input 5 Please be sure that all wirings are fastened Figure 4 4 3 DC Input Wiring 4 4 4 AC side wiring CAUTION Caution risk of danger When connecting the AC grid cut off the circuit breaker at the AC side to ensure that the AC wire connecting to te...

Page 15: ...he user needs to monitor the operating status of DC power generation system we provide single machine and multi machine control programs and diversified communication interfaces for customer s selection 4 5 1 RS485 communication The inverter through RS485 tandem is connected with the PC for communication through RS485 RS232 adaptor Inside the PC a multi machine monitoring software ShineNet indepen...

Page 16: ...ion Inspection List Pilot operation 5 The chapter will introduce the procedure of pilot operation including checking battery voltage input and output connecting other preparation working 5 1 Relevant requirements Before pilot operation the installation conditions of the equipment shall be examined thoroughly in particular whether voltages at DC and AC ends are consistent with inverter s requiremen...

Page 17: ...power off In operation process of the inverter it can be powered off by clicking OFF button on the screen At this moment the inverter stops working CAUTION After manual power off the machine must be powered on manually otherwise the inverter is unable to power on 5 4 Pilot operation completion The following procedures shall be carried out after the inverter is normally in operation Procedure 1 Ins...

Page 18: ...unication state station number and system time is displayed at the top of each page of the LCD Each page has five commonly used function keys run data historical information system settings Home at the below of the page The five commonly used keys corresponding sub menu are under the button and it will be marked green after selected 6 2 1 Home page Clicking Home button in any interface will enter ...

Page 19: ... default language is Chinese Time settings system time setting if the date and time displayed on LCD is not inconsistent with the actual date and time they can be modified here Device Information This page shows the manufacturer inverter serial number hardware and software version information and the date of manufacturing Maintenance the interface requires a password to login It is for electrician...

Page 20: ...the corresponding sub menu interface The default interface is the real time data interface Insert USB Disk on the back of the LCD display and the real time operation data will be stored in the USB Disk in every minute Inverter will create a CSV format file every month in the USB disk for data storage Real time data current DC power generation parameters and real time data including the grid voltag...

Page 21: ...lt_Fault AC_UV_UnderVolt_Fault No information 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 AC_GridCurr_DcHigh_Fault AC_GridCurr_High_Fault AC_L_Curr_High_Fault AC_Overload_Fault Smoke_Alarm_Fault GFDI_HallSense_Fault GFDI_AirSwitch_Fault Inductor_Rly_Fault LVRT_Fault Module1_OverTemp_Fault Module2_OverTemp_Fault...

Page 22: ...ust screen replacement 1 The front and back cover can be seen after opening the front and back cover of the inverter 2 Open front and back dust cover from the bottom of the dust cover 3 Take away the dust screen and insert a clean one 4 Place the dust cover in the original place and fix it Figure 7 1 Dustproof device No information 85 86 87 88 89 Batt_UnderVolt_Warning AC_WU_OverVolt_Rmt_Warning A...

Page 23: ...C and DC disconnected for at least 5 minutes in order to avoid electric shock 7 2 Regular maintenance The inverter will not cause environmental pollution since the all the components meet the requirements of environmental protection According to environmental protection requirements user shall dispose the inverter in accordance with the relevant laws and regulations Appendix 8 VMAX DC absolute max...

Page 24: ...any inverter which has been subjected to Misuse abuse neglect or accident Alteration improper installation or application Unauthorized modification or attempted repairs Insufficient ventilation of the product Transport damage Breaking of the original manufacturers seal Non observance of ATESS installation and maintenance instruction Failure to observe the applicable safety regulations Power failur...

Reviews: