 Xeon Installation Procedure

Xeon Processor Installation

Step 1: Install the Baseboard

A metal baseboard is required to add stability to the motherboard. A rubber pad is
placed between the metal board and motherboard to provide insulation to prevent
shorting. Align the rubber pad over the metal baseboard so that the holes match.
Align the ASUS XG-DLS motherboard over the rubber pad and metal baseboard so
that the screws match up with the motherboard’s screw holes. Place and tighten
three captive nuts in the corner locations circled.

Step 2: Install Retention Mechanisms

Place the retention mechanisms’ holes over the screws and the Slot2. Screw four
captive nuts onto the screws as circled in the picture on the right. Do not place the
other captive nuts yet.

(Item 3) Retention Mechanism

Two retention mechanisms installed

(Item 4) Captive Nut

Four installed captive nuts

(Item 1) Metal Baseboard

(Item 2) Rubber Pad

ASUS XG-DLS Motherboard

Summary of Contents for XEON

Page 1: ...e following pictures are for reference only and are not to size The design and color of your items may be slightly different You should check to see that you have the following items with your motherboard Item 6 Retention Mechanism Brace Bar x 2 Item 7 Front Side Bus Termination Module Item 8 Retention Mechanism Cap x 2 Item 9 Retention Mechanism Support Frame x 2 Item 5 Cartridge Lifter x 4 Item ...

Page 2: ...gn theASUS XG DLS motherboard over the rubber pad and metal baseboard so that the screws match up with the motherboard s screw holes Place and tighten three captive nuts in the corner locations circled Step 2 Install Retention Mechanisms Place the retention mechanisms holes over the screws and the Slot2 Screw four captive nuts onto the screws as circled in the picture on the right Do not place the...

Page 3: ... two holes at each top corner Item 6 Retention Mechanism Brace Bar Retention mechanism with brace bar on top One retention mechanism with brace bar installed Both retention mechanisms with both brace bars installed One lifter being inserted over the cartridge from a vertical position Item 5 CPU Lifter Half colapsed lifter after installation The lifter should freely rise and lower Step 5 Install a ...

Page 4: ... nuts in case you loose any The right end of the cap enters the retention mechanism and a click is heard as it snaps in place The cap must go in from the left side first toward the ATX connectors The left side has one dot while the right side has two dots Item 8 Retention Mechanism Lock Bar The processor raised out of the slot 2 connector by the reverse force of the lifters as they are pryed to a ...

Reviews: