INSTALLER: LEAVE INSTRUCTIONS WITH BUILDING OWNER

CAUTION

1. Disconnect all power before beginning 

installation to prevent electrical shock 
and equipment damage.

2. Installer must be a trained, experienced 

service person.

3. All wiring must comply with 

applicable local electrical codes, 
ordinances and regulations.

4. Maximum wire size is 14AWG.

2-Pin Jumper

SOL

1

2

3

4

3

2

1

120VAC Circuit Board

4-Pin
Jumper

Earth

(+)

(-)

Input
Power

Test Switch

Openings for surface
or concealed wiring

Terminal Strip for

Power Input Connection

Header for Solenoid
Connection

Fuse (PTO125V)
125V / 1/2A

STAND ALONE UNIT

(120VAC shown)

- Wire stand alone unit to appropriate power supply and fire 

system.

- Refer to data sticker on back of hook-up box for proper input 

power voltage and current specifications.

- Solenoid Connector must be attached to Header on circuit board 

before hold open will function.

- Energize power supply. Current draw of .074Amps max per unit.
- Open door to hold open point. Door should hold open.
- Depress Test Switch. Door should close and latch.
- Test Switch is a momentary switch. Once released, hold open 

should re-energized.

- Adjust closer spring power to insure proper latching.

Wiring Diagram for Master to Companion

Companion Unit - 24v ONLY 

(2499 / 9-2499)

Master Unit -120v or  24v Input  

(12-2499)

To Solenoid

To Solenoid

7 6 5 4 3 2 1

8 7 6 5 4 3 2 1

1

4

Field Wiring Provided by Others

Wire Nut or Splice Connector (Provided)

- Companion units are designed to work with 12- smoke detector 

units.

- Wire companion unit to smoke detector unit as shown on wiring 

diagram.

- Do not disconnect any existing wires on smoke detector unit’s 

terminal strip.

- Energize power supply. Current draw of .074Amps max per unit.
- Open door to hold open point. Door should hold open.
- Depress Test Switch on master unit. Doors should close and latch.
- Test Switch is a momentary switch. Once released, hold open 

should re-energized.

- Adjust closer spring power to insure proper latching.