Installation and Maintenance Instructions for  
N5500 Capsule Pressure Gauges

© Ashcroft Inc. 2019, 250 East Main Street, Stratford, CT 06614-5145, USA, Tel: 203-378-8281, Fax: 203-385-0357, www.ashcroft.com 

All sales subject to standard terms and conditions of sale. n5500_gauge_im_RevA_03-10-21

3

6.2 Installation

 

Devices with a blow-out require a minimum spacing to the rear 
(1.0˝).

•  Connection to be undertaken by authorized and qualified 

personnel only

•  Use only with the mechanical process connection provided 

– regarding the configuration, see order code on the device 
type label, with a matching threaded seal.

•  When connecting the device, the pipes must be depressurized.

•  The pressure metering pipe must be kept as short as possible 

and laid without sharp bends, to avoid the occurrence of 
delays.

•  Devices with a blow-out require a minimum spacing to the 

rear (1.0˝).

6.3 Start Up

The precondition for start-up is proper installation of all elec-
trical feed lines and metering pipes. All connecting lines must 
be laid such that no mechanical forces can act on the device.  
Before start-up, the seal on the pressurized connection line 
must be checked

 

6.4 Zero point adjustment

 

The N5500 are supplied calibrated, so that as a rule there is no 
need for calibration works at the installation point. Zero point 
adjustment on site is standard. For this, proceed as follows:  
Depressurize the pressure metering pipe. 
•  Open the bayonet ring and remove ring and window. 

•  Hold the pointer in place while turning the screw, until the 

pointer (after releasing again) has the correct position.

•  Close the case again and pay attention to correct fit of 

window, gasket and bayonet ring.

•  Liquid filled gauges must  

be demounted before the  
zero point adjustment can  
be done (on a horizontal  
area to prevent leaking).

7 SERVICING

The N5500 is maintenance-free. However, to ensure reliable 
operation and a long lifetime, it is recommended that it is 
checked regularly.

7.1 Safety

When undertaking servicing work on the N5500, the pressure 
lines must be depressurized and the plant secured against being 
switched on again.

7.2 In-service inspection

 

The check on function and recalibration is carried out at regular 
intervals, depending on the application. The precise testing 
cycles should be adjusted in line with the operating conditions 
and ambient conditions. In the event of various device 
components interacting, the operating instructions for all other 
devices should also be taken into account.

•  Check on display.

•  Check on function, in conjunction with downstream 

components

•  Check of pressurized connection pipes for seal condition.

•  Remove gauge from service should any leaks be identified.

7.3 Cleaning and maintenance

 

Cleaning is carried out using a non-aggressive cleaning agent, 
with the ventilation valve closed and respecting the protection 
category of the N5500.

8 APPENDIX

The N5500 is maintenance-free. However, to ensure reliable 
operation and a long lifetime for the N5500, we recommend 
that it is checked regularly.

8.1 Data sheet for capsule pressure gauge N5500

Detailed data sheet is available from the Ashcroft website. 
Please visit www.ashcroft.com for more details