7. Lay the scaffold boards side-by-side on top of the ASAP platform until the stairway opening
is completely covered. (See figure 5)
8. The working platform is now complete and is safe to use for anyone needing to work over the
stairwell opening. (see figure 6)
DO NOT EXCEED THE
SWL
AT ANY TIME.
9. The timber stud walls, and bulkhead can now be constructed leaving the platform in place.
To do this the sole plates on the timber stud walls surrounding the stairwell need to be notched
over the L brackets of the ASAP beams. (See figure 7 and 8)
10. Once a surrounding timber stud walls have been fitted, and the temporary fall from hight mid
rail has been installed. The ASAP system can be removed. (See figure 9)