61
BOILER PROTECTION DEVICES
Central Heating circuit
1 01
Overheat
1 03
Insufficient circulation
1 04
1 05
1 06
1 07
1 08
Insufficient water (request filling)
1 09
System pressure > 3 bar
1 10
C.H. Flow temp. probe circuit open / short circuit
1 12
C.H. Return temp. probe circuit open / short circuit
1 14
External sensor circuit open / short circuit
1 18
Heating delevery probe problem
1 P1
Insufficient circulation indication
1 P2
1 P3
1 P4
D.H.W. circuit
2 05
DHW In Probe Open Circuit
Internal P.C.B.’s
3 01
EEPROM error
3 02
Comunication error
3 03
Main P.C.B. error
3 04
Too many (> 5) resets in 15 minutes
3 05
Main P.C.B. error
3 06
Main P.C.B. error
3 07
Main P.C.B. error
3 P9
Sched.Maintanace-Call Service
External P.C.B.’s
4 11
Room sensor circuit open or short circuit ZONA 1
Ignition and Detecion
5 01
No flame detected
5 02
Flame detected with gas valve closed
5 04
Flame lift
5 P1
1st Ignition Failed
5 P2
2nd Ignition Failed
5 P3
Flame cut-off
Air Inlet / Flue gas outlet
6 07
Air pressure switch closed permanently
6 08
Air pressure switch OFF Fan ON
6 P1
Delay in air pressure switch closing
6 P2
APS close-open
Table summarising error codes
Combustion Analysis
To perform the analysis of combustion must be installed
accessories with flue/air test point (see Fig. Below).
Using the test point to detect the temperature of the flue gases
and combustion air, concentrations of O2 and CO2, etc.
It is possible activate the flue test mode by pressing and holding
the RESET button for 10 seconds on the display appear
(see parameter 270)
The boiler will return to normal operation after 30 minutes. The
boiler can be returned to normal operation sooner by switching
the boiler off and on again. Close properly test points after the
analysis of combustion.
Product of Combustion - Discharge Monitoring
In the boiler, it is possible to monitor the correct operation of the
flue exhaust/air intake, checking for a loss of general pressure
in the system. Through the use of a differential manometer
connected to the test points on the intake/exhaust pipes (see
Fig. Below)
, it is possible to detect the ∆P of operation of the air
pressure switch.
The value detected should not be less than 0.47 mbar (24 kW)
under conditions of maximum thermal power in order for the
boiler to function properly and without interruption.
TO PERFORM THE ANALYSIS OF
COMBUSTION MUST BE INSTALLED
ACCESSORIES WITH FLUE TEST POINT
(SEE FIG. BELOW).
FOR MORE INFORMATION ON FLUE
ACCESSORIES REFER TO THE CATALOGUE
FUMES ARISTON.
Summary of Contents for 3636085
Page 42: ......