background image

Before commencing installation, it is essential that the instructions below are read and 
understood and that you have all the necessary components (shown overleaf). Prior 
to installation, ensure all additional guides supplied with this product are read and 
understood. 

Failure to install the product in accordance with these instructions may adversely affect 
the warranty terms and conditions. Do not undertake any part of this installation unless 
you are competent to do so. Prior to starting, ensure that you are familiar with the necessary 
plumbing and wiring regulations required to install the product correctly and safely.

The Quartz Smart Valve

TM

 must be isolated from the mains power supply prior to 

installing the wired remote.

 

 

!

INSTALLATION

Prepare a suitable route and install the 10m low voltage data cable. On the Quartz

 

Smart Valve

TM

 

side, allow sufficient length for plugging into the Quartz

 

Smart Valve

TM

 socket. On the wired 

remote side we recommend a minimum length of 70mm including the connector plug. 

Ensure the data cable is the correct way round as both ends differ in type of connection used.
Data cables must be protected by suitable sheathing or conduit in the event of servicing 
and maintenance.
A cut out is provided in the back plate to facilitate surface sited cable entry if preferred. 

 

 

!

2

Using the back plate as a template, mark the position of the fixing 
screws and a Ø20mm hole for the data cable rear entry point. 
Prepare suitable wall fixings to accommodate no. 8 non-rusting 
countersunk head screws of a suitable length (not included). 

1

Wiring diagram - single outlet

Apply a thin bead of silicone sealant in the mastic groove at 
the rear of the mounting plate and pull the data cable through 
before securing the back plate to the wall using suitable no. 8 
non-rusting countersunk screws. 

3

5

Locate the remote assembly onto the back plate with the 
graphics in a diagonal position as illustrated. Rotate the remote 
clockwise so the graphics are in the horizontal position to lock 
the unit in place. 

To release the remote, insert a small flat bladed 
screwdriver into the small opening at the 7 o’clock 
position to release the locking mechanism, and rotate the 
remote face anti-clockwise. 

Before any electrical adjustment is attempted, the 
electricity supply must be turned off at the mains switch. 
Electrical installation may only be carried out by a 
qualified person.

 

 

!

6

The Quartz

 

Smart Valve

TM

 features a secondary data cable socket 

next to the main data cable connection for use with the remote. 
Carefully snap and remove the entry pillar and connect the cable 
into the socket as shown. 

For wired remotes used in conjunction with divert products, the cable plugs directly into 
the diverter. 
Quartz™ divert wired remotes can only be used with divert products. 
Please refer to the Divert Installation Guide for further information.

 

 

!

7

Prior to commissioning the wired remote, please refer to the installation instructions provided 
with the main product to complete the installation of the Quartz

 

Smart Valve

TM

.

WIRED REMOTE 

Commissioning

1.  Reconnect the power supply to the Quartz

 

Smart Valve

TM

.

2.  Turn the shower system on using the main controller. 

The LED light ring will flash simultaneously with the remote light ring, until the desired 
temperature has been reached. When both LED lights remain constant, turn the 
shower off using the main controller.

3.  Repeat the above process using the remote rather than the main controller ensuring 

the LED lights flash and remain constant simultaneously.

User guide
Single outlet system

1.  Press the button on the wired remote to turn the shower on. 
2.   The flashing to steady LED display advises when the  

temperature selected by the main controller has  
been reached.

3.   Turn the shower off either by pressing the main controller  

or remote button.

Dual outlet system

1.  Press the button on the remote on the wired remote to turn the shower on.
2.   The shower system will operate as determined by the outlet selected during the 

diverter commissioning procedure.

3.  If required, push and hold the remote button for 3 seconds to stop the 1st outlet and 

start the 2nd outlet.

4.  The flashing to steady LED display advises when the 

temperature selected by the main controller has been 
reached.

5.  Turn the shower off either by pressing the main 

controller or remote button.

After installation

Run through the wired remote operation with the user and hand them this guide, as well 
as the main installation and user guide, if applicable. 
Complete and post the guarantee card or register online at www.aqualisa.co.uk

Cleaning and maintenance

Your wired remote should be cleaned using only a soft cloth and washing up liquid.

DO NOT USE ABRASIVE CLEANERS
Cleaning and maintenance should not be undertaken by children without supervision 
by a person responsible for their safety.

Quartz

TM

 images shown for illustrative purposes only. 

4

Lining up the key way, push the data cable plug into the back of 
the remote assembly, ensuring both rubber skirts are recessed 
into the connection (see diagram below), using a blunt flat bladed 
screwdriver or similar tool if required. To make a water tight 
fitting, ensure the rubber seal is no longer visible. 

If fitting a Rise

TM 

product, please refer to main Rise User Guide for further 

operating instructions.

Although the Quartz Smart Valve

TM

 complies with all relevant EMC standards, if incorrectly 

sited, it may interfere with digital TV reception. Please follow the recommendations below to 
minimise this effect.
If TV interference is an issue a service kit is available (part no: 652102).
See recommended layouts below. 
Images of Quartz Smart Valve

TM

 for illustration only, refer to main installation guide for orientation. 

Valve colour may vary – the Original Quartz

TM

 valve being black, and the Quartz Smart Valve

TM

 

being orange.  

• Route cables separately, and as far apart from each other as possible.
• Aerial to point away from the Quartz Smart Valve

TM

.

• Ensure the distance between the Quartz Smart Valve

TM 

and the aerial is as large as possible.

DIGITAL TV INTERFERENCE

AERIAL

LARGEST POSSIBLE DISTANCE

DATA 

CABLE

POWER 

CABLE

CABLE 

TO  TV

HIGH PROBABILITY 

OF INTERFERENCE, 

BOTH RADIATED 

AND CONDUCTED

POWER 

CABLE

CABLE 

TO  TV

DATA 

CABLE

AERIAL

SHORT DISTANCE

LAYOUT WHICH COULD CAUSE PROBLEMS

LOWEST PROBABILITY OF INTERFERENCE

Wiring diagram - dual outlet

Quartz Rise Remote Installation Guide 704025 - Issue 2.indd   2

15/10/2018   12:37

Reviews: