1.

  Remove one nut from each anchor insert. 

Place the anchor inserts through the larger hole 
of the anchor jig plate. Thread the removed nuts 

back onto the anchor inserts. The anchor plate should be 
sandwiched between the two nuts on each anchor insert.  

SEE FIGURE 4

2.

 Mark out a section of the pool deck that you are 

removing. Plan on removing at least
4 feet 3 inches by 4 feet 3 inches.

3.

 Cut along your marks with a diamond blade concrete 

saw.

4. 

 Using the sledge hammer break up the concrete within 

the cut area and remove the pieces.
  

5.

  Install rebar in the open area of the deck. Tie the rebar 

into the existing deck if possible. 

SEE FIGURE 5

6.  

Set the anchor system in place. For ADA 

compliance and clearance, make sure the center 
of the large anchor jig plate hole is between 22.5 
and 38 inches from the pool’s edge.

 SEE FIGURE 5

7. 

 Using the string line or a straight edge & level, 

confi rm the top of each anchor body is level with 
the 

FINISHED

 deck surface. Each anchor body can 

be individually adjusted by turning the nuts with 
a large wrench.

8.

  Bond the anchoring system according to your 

local code requirements by using the bonding lug 
on the anchor plate.

 SEE FIGURE 5 

(See NEC Article 

680.26)

9.

  Pour concrete and fi nish the pool deck surface.

10.

  Once the concrete has cured, the lift is ready 

to be mounted to the anchoring system.

1" X 4"

ANCHOR INSERT (3)

1" HEX NUT (6)

ANCHOR JIG-PLATE

#10-24 NYLOCK NUT

Cu BONDING LUG

#10-24 X 3/4"

CAP-SCREW

1/4" FLAT WASHER

1/4" X 3/4" PAN-HEAD

SIDE VIEW (ASSEMBLED)

FIGURE 4

•  Concrete saw with diamond blade

•  Tape measure

•  4’ long straight edge or chalk line

•  Sledge hammer

•  Cold chisel

•  Large adjustable wrench

•  Torpedo level

•  String Line

•  Concrete & concrete 

    fi nishing tools

•  #5 rebar

You Will Need:

Anchor Installation: Saw-Cut Retro-Fit

 51" 

 51" 

12"

TYP

22 1/2" MIN

TO

38" MAX

POOL WALL OR

FURTHEST

OBSTRUCTION

#5

REBAR

8-AWG SOLID-

COPPER WIRE

(ATTACH TO

BONDING-GRID)

BONDING

LUG

LABEL

 4" 

 6" 

FLUSH W/ DECK

#5 REBAR E-W (5 PCS)

DRILL & EPOXY INTO EXISTING

SLAB (4" MIN EMBED) 

2500 PSI MIN.

*SETBACK DIMENSIONS ARE FOR 

FLAT DECK 

APPLICATIONS.

 FOR SLOPED DECKS OR OTHER FEATURES, CONTACT AQUA

 CREEK BEFORE INSTALLATION.

FIGURE 5

NOTE: 2500PSI MINIMUM STRENGTH 6” 

THICK OR MORE CONCRETE IS REQUIRED

6

Summary of Contents for Ambassador Pool Lift

Page 1: ...ult supervision NEVER apply direct water pressure to the electronics NEVER use the lift with a dry pool ADA COMPLIANT Check entire box and all packing materials for parts Before beginning assembly rea...

Page 2: ...AmbassadorLift Table of Contents PAGE DESCRIPTION PAGE DESCRIPTION 2 Ambassador Components 10 Basic Troubleshooting 3 ADA Installation Guidelines 11 Battery Test Cable Instructions 4 5 Anchor Installa...

Page 3: ...inches from the pool edge Deck slope no greater than 1 48 The seat must submerge at least 18 inches into the water The lift should be installed at a location with 42 48 inches of depth deck to pool o...

Page 4: ...nstructions on page 6 3 Remove the nuts and the black protective coverings from the threaded anchor inserts 4 Thread the 1 2 inch hex bolts and flat washers through the smaller anchor jig plate holes...

Page 5: ...For more information see NEC Article 680 26 6 Test fit the anchor assembly into the pre drilled holes and use a torpedo level to ensure your anchoring system is level SEE FIGURE 3 7 Remove the anchor...

Page 6: ...h anchor body can be individually adjusted by turning the nuts with a large wrench 8 Bond the anchoring system according to your local code requirements by using the bonding lug on the anchor plate SE...

Page 7: ...g on the anchor jig plate Bond the system according to your local code requirements See NEC Article 680 26 SEE FIGURE 5 PAGE 6 6 Pour your concrete and finish the pool deck surface 7 Once the concrete...

Page 8: ...arge for 24 hours Make sure the orange charge light illuminates when the battery is being charged When the orange charge light shuts o the battery is fully charged 5 Remove the fully charged battery f...

Page 9: ...install the legrest 1 Insert the legrest assembly into the 2 x 2 square tubing that supports the chair until the plastic insert of the legrest assembly sits flush against the end of the 2 x 2 tube 2 U...

Page 10: ...there is corrosion clean with Scotch BriteTM pad Put some dielectric grease on the contact points before reattaching the battery Note If you feel your lift is malfunctioning due to a faulty battery or...

Page 11: ...onnector for connecting to the control box or to the battery charger The battery connector is not suitable to check the battery voltage as it is very hard to probe the connector without shorting out t...

Page 12: ...Copyright 2019 Aqua Creek Products All Rights Reserved Revised 6 17 19 PinchPointLocations CAUTION PINCH POINT AREA 12...

Page 13: ...a liberal coat of car wax to maintain the lift s finish Check all Warning and Cautionary labels to make sure they are not faded or worn Replace as needed ProperCareofPool SpaLifts PROPER CARE NOTES Us...

Page 14: ...NZE 1 2 TT 1001 1 22 1 THRUST WASHER 3 4 BRONZE WASHER BRONZE 3 4 TT 1205 1 23 2 BRB FL 50 3 BUSHING BRONZE FLANGE 1 2 X 5 8 X 3 8 X 1 8 24 1 F 45ACB C COVER ACTUATOR WATER RESISTANT 25 2 PPB CCB 10 B...

Reviews: