WARNING!
For safety, the power outlet used for powering the instrument
must be accessible at all times. See “Instrument clearances“ on page 5 for
information about the space needed between the wall and the instrument. In
case of emergency, you must be able to immediately disconnect the main power
supply to all the equipment. Allow adequate space between the wall and the
equipment so that the power cords can be disconnected in case of emergency.
• Electric receptacle with grounding capability
• Maximum power dissipation: ~960 W (not including computer and monitor)
• Mains AC line voltage tolerances must be up to ±10 percent of nominal voltage
Device
Rated voltage
Circuit
required
Rated
frequency
Rated
power
Instrument
100–240 ±10% VAC
[1]
10 A
50/60 Hz
960 W
Computer (laptop)
100–240 ±10% VAC
10 A
50/60 Hz
90 VA
Computer (desktop)
100–240 ±10% VAC
10 A
50/60 Hz
125 VA
Monitor
65 VA
[1]
If the supplied power fluctuates beyond the rated voltage, a power line regulator may be required. High or low
voltages can adversely affect the electronic components of the instrument.
Electrical
requirements
Site requirements
8