4.3 

Fit the DHW Unit 

 

(1) 

Drill four fixing holes (5mm dia) through the back panel of the unit to accept 
the No. 8 screws supplied. 

 

(2) 

Hold the unit on the wall in the required position ensuring it is level and mark the 
position of the fixing holes.  Then drill the fixing holes (6mm dia) in the wall to 
accept the No.8 wall plugs. 

 

(3) 

Using the screws supplied secure the unit to the wall. 

 
4.4 

Fit the Thermostat and Sensor  (Refer Diagram 4.2.3) 

 

(1) 

Unscrew the plastic cap on the hot water control valve body and remove. 

 

(2) 

Locate and secure the thermostat onto the valve body by tightening the loose  

 

nut by hand onto the thread of the body. 

 
(3) 

With care unwind the capillary tube and position the sensor onto the location 
provided on the outlet pipe from the heat exchanger. 

 

(4) 

Secure the sensor in position using the tape supplied.  Then locate the 
insulation supplied around the sensor and secure with the two straps provided. 

 
4.5 

Connect the Pipework  (Refer Diagram 4.2.3) 

 

(1) 

Thoroughly flush out ALL the pipework. 

 

(2) 

Connect the 15mm isolating valve to the cold inlet pipe of the unit and then 
connect the domestic hot water pipework. 

 

(3) 

Using a ‘T’ connection, connect the central heating pipework to the DH flow and 
return of the DHW unit and fit the CH valve and isolating valves in the positions 
shown in the diagram 2.6. 

 

Note:  Ensure the CH valve is located within 600mm of the DHW unit. This will 

allow it’s cable to be directly connected into the unit’s control box. 

 

(4) 

Connect the 22mm strainer supplied to the DH flow pipe and then connect the 
two isolation valves to the DH flow and return pipes. 

 

Note:  Ensure the strainer is always fitted after the valves. This will allow 

isolation for cleaning of the filter (Refer diagram 2.6) 

 
4.6 

Connect the CH Valve Electrical Cable  (Refer Sect 2.4) 

 

(1) 

Gain access to the DHW terminal block by releasing the 4 screws securing 
the control box cover. 

 

(2) 

Pass the CH valve’s electrical cable through a cable clamp and connect the 
wires as follows (refer to diagram 2.4); 
Brown to terminal 7, Black to terminal 9, Blue to terminal 3, Grey to terminal 13, 
Orange to terminal 12, White is not used, therefore terminate safely. 
 

(3) 

Tighten the cable clamp by hand until the cable is secured. 

 

 

8

Summary of Contents for Alpha Plus DH Units

Page 1: ...tructions for Installation Alpha Plus DH Units for Domestic Hot Water and Direct Central Heating Alpha Therm Ltd Nepicar House London Rd Wrotham Heath Kent TN15 7RS Leave these instructions with the U...

Page 2: ...ter cover Part no 6 3000400 enclosing the main components of the DHW unit is available if required The above district heating units comply with the following requirements Electrical requirements of BS...

Page 3: ...tput 15 to 20 l min Max Flow Rate at 35 C rise approx 12 l min Min required Flow Rate 2 5 l min Adjustable Outlet temperature up to 60 C Max Outlet Temperature approx 62 C Mains inlet connection 15mm...

Page 4: ...fuse 3 A Power Consumption 6W 2 5 Installation Dimensions of assembled Unit Height 500mm Including Cover Width 300mm Depth 220mm Min clearances required Top 5mm Bottom 200mm Sides 5mm Front 450mm Asse...

Page 5: ...2 6 Schematic Diagram 5...

Page 6: ...he district heating water flow to the heat exchanger When the flow switch senses that hot water is no longer required the DHW valve closes 3 2 Direct Central Heating If there is a call for heating fro...

Page 7: ...t must be installed vertically on a flat vertical wall which is capable of supporting its weight 2 Decide upon the position of the unit taking into consideration the clearances required Refer Sect 2 5...

Page 8: ...2 Connect the 15mm isolating valve to the cold inlet pipe of the unit and then connect the domestic hot water pipework 3 Using a T connection connect the central heating pipework to the DH flow and re...

Page 9: ...way Changeover switching The procedure is as follows 1 Gain access to the terminal block as in 4 6 1 2 Pass the mains supply cable through the cable clamp and connect as follows Brown to L Blue to N...

Page 10: ...6 Ensure terminal block 2 is correctly located into the control box as shown below 7 Replace the control box cover and secure with the 4 screws previously removed 10...

Page 11: ...ing if necessary 3 Fill the Direct Central Heating system Open the CH flow and return isolation valves and allow DH water to flow into the system Vent each radiator etc to remove any air and check for...

Page 12: ...ipe 4 DH Flow 1 019924 Pipe 6 DH Return 1 020254 Pipe 7 22 x 60mm 6 3000144 Elect Plug Flow Switch 6 3000111 Relay Control box 6 3000112 Control Box 6 3000110 DHW CH Valve 6 3000120 Thermostat Body 6...

Page 13: ...13...

Page 14: ...These instructions have been carefully prepared but we reserve the right to alter the specification at any time in the interest of product improvement Alpha Therm Ltd 2005 Part no 6 3000160 04 05 14...

Reviews: