4.8 Integrated Battery Trays
The CXPS-E3 system is designed to integrate battery trays below the power system. These battery trays can accept
standard 12V mono-blocks ranging in height from 6RU-8RU. The battery trays are factory installed and pre-wired for
ease of installation. They can be configured for with or without battery breakers as Over Current Protection Devices
(OCPD). The battery breakers are installed within a breaker housing on the side of each battery tray. The breaker
sizes and its associated cabling can range from 100A–250A.
When battery trays are ordered for systems without a Battery Low Voltage Disconnect (BLVD), the battery cable
landing bus bar kit will need to be ordered. This kit provides a secure location to terminate each individual battery
tray cable to the main power system bus enabling a neat and clean install. In addition, this kit provides sufficient ac-
cess to customers in the event that a battery tray and its associated cabling needs to be added in the field on a live
plant.
4.9 Battery Landing Busbar Kit
The CXPS system can be purchased with an optional Battery Landing Busbar Kit (0250030-550) which provides
landing locations for 3 pairs of back-to-back cable lugs (See Figure 16). This kit is customer installed at time of sys-
tem installation.
Figure 15 — Integrated Battery Tray