Quick Install Guide

5

C613-04030-01 REV H

For the SwitchBlade 4 chassis (AT-SB4104):

Unless replacing an existing line card, choose the empty line card bay that 
is closest to bottom of the chassis. This provides optimum cooling. Line 
card bays are bays 1 to 4.

For example, fill line card bay 4 first, and bay 1 last. Bay numbers can be 
found on the chassis, right of each bay.

Although line cards will operate in any combination of line card bays, filling the bays in 
the order described above provides optimum cooling.

Do not attempt to install a line card in a switch controller bay (bay A or B). 
Attempting to install a line card in a switch controller bay is likely to damage 
the line card and chassis.

4.

Prepare the line card

In an antistatic environment, remove the line card from its packing 
material.

 

Be sure to observe ESD precautions.

Do not attempt to install a line card without observing correct antistatic 
procedures. Failure to do so may damage the line card and chassis. If you are 
unsure what the correct procedures are, contact your authorised Allied Telesyn 
distributor or reseller.

An ESD socket is provided on the front panel of the SwitchBlade chassis (see Figure 1 
on page -5)
. This socket provides a connection for an ESD wrist strap.

Figure 1: ESD socket on the SwitchBlade 8 chassis.

5.

Remove the line card bay faceplate or existing line card

To remove a blank faceplate:

Loosen the faceplate’s two Phillips mounting screws until they disengage 
from the chassis, then remove the faceplate.

Keep the faceplate for future use. If you should remove a line card, replace the faceplate 
to prevent dust and debris from entering the chassis and to maintain proper airflow.

Summary of Contents for AT-SB4311

Page 1: ...SwitchBlade Line Card Quick Install Guide...

Page 2: ...changes in specifications and other information contained in this document without prior written notice The information provided herein is subject to change without notice In no event shall Allied Te...

Page 3: ...X fibre SFP AT SB4541 1 port 10GBASE LR XFP Information on installing switch controllers can be found in the SwitchBlade Switch Controller Quick Install Guide Quick Install Guide updates can be downlo...

Page 4: ...l characteristics of hot swapped interfaces Follow these steps to install a line card 1 Read the safety information The SwitchBlade Safety and Statutory Information booklet includes all relevant safet...

Page 5: ...tic environment remove the line card from its packing material Be sure to observe ESD precautions Do not attempt to install a line card without observing correct antistatic procedures Failure to do so...

Page 6: ...card guides see Figure 3 on page 7 Line cards are mounted vertically in the SwitchBlade 8 AT SB4108 chassis and horizontally in the SwitchBlade 4 AT SB4104 chassis With the ejector levers in the unloc...

Page 7: ...niature pluggable transceivers such as GBICs SFPs and XFPs install the transceivers Slide each transceiver into its appropriate slot and press it firmly into place A range of pluggable transceivers ha...

Page 8: ...bps activity is occurring Amber A 10 100 Mbps auto negotiating link is open The L A LED for port 1 briefly lights at switch power up or when the card is hot swapped Flashing amber 10 or 100 Mbps activ...

Page 9: ...ed Table 4 LEDs on the AT SB4442 V2 24 Port SFP Gigabit Line Card LED State Function SFP Link Activity Steady Green Glow For fibre SFPs The SFP is able to send and receive a light signal For copper SF...

Page 10: ...e SwitchBlade Hardware Reference which provides detailed information on the switch and its hardware features The SwitchBlade Software Reference which provides detailed information on configuring the s...