Operational requirements of open vented systems:
In order to maintain a
safe and economical operation, open vented heating systems shall be equipped
with:
20
x
Water level indicator
x
Temperature indicator (% 20 higher then the operating temperature and
mounted in the flow pipe of the system)
x
Devices for controlling the operation temperature to adapt the heat
supply to the heat demand. The maximum set-point of the temperature
controller shall not exceed the maximum operating temperature of
the boiler.
x
Heating system shall be equipped with devices to fill the system and
provide adjustment of the water level. Connections to a drinking water
supply system shall comply with prEN 806-2, e.g. back flow prevention
x
An adequate supply of combustion air is important for safe and clean
combustion. For open flue heating systems with a total rated output
higher than50 kW, the rule regarding the supply of combustion air is
treated as satisfied, if the cross-section of the aperture leading into the
open air is at least 150 cm² and is 2 cm² larger for each kW of rated
output above 50 kW.
Summary of Contents for ACK2
Page 1: ...Operation Manual ACK2 ACK3 HEATING SYSTEM BOILERS WITH LIQUID GAS FUEL...
Page 2: ...Code No A 4 1 3 i Published on 210910 Revision No 210910...
Page 4: ......
Page 33: ...BOILER CONTROL PANEL WIRING DIAGRAMS 33...
Page 36: ...ANNEXES 36...
Page 37: ...37...
Page 38: ...38...
Page 39: ...39...
Page 40: ...40...
Page 41: ...41...