BU-0101704 R3
33
2. Slide the underfloor auger through the bin wall cutout and align the center sump vertical gearbox shaft hole
exactly at the bin center point (C) (see
Section 6.2 – Bin Floor Preparation on page 26
). Insert the top and
bottom access panels in the center sump temporarily to aid positioning (see
Figure 16.
Install Underfloor Auger in Position
3. Level the underfloor auger using shims (not supplied) at every floor mount bracket. The underfloor auger
must be level within 1/4” (6 mm) per 10’ (3048 mm) of span or not more than 1/2” (13 mm) for whole
underfloor auger. This will prolong life and ensure smooth operation.
4. Anchor the underfloor auger to the bin floor using concrete anchor bolts through the holes in the factory-
installed anchor legs. The anchor bolts are purchased separately according to type (see
).
a. Install two concrete anchor bolts in the anchor legs nearest the center sump.
b. Install the remaining concrete anchor bolts in the anchor legs at equal intervals along the remainder of
the underfloor auger.
6.4. Install the Bin Adapter
Note
The bin adapter creates a seal to minimize aeration and heat losses (when applicable) and keeps snow
and rodents out.
Æ
1.
For a Westeel or Twister bin:
If not done so already, remove the 1/4” x 1-1/2” bolts (1) and nylon locknuts
(2) from the coupler (3) of the lower gearbox control rod (see
C
C
EASYFLOW2 (100 SERIES) – FARM TUBE BIN UNLOAD SYSTEM