BU-0101704 R3
29
Figure 10.
Install Underfloor Auger in Position
3. Level the underfloor auger using shims (not supplied) at every floor mount bracket. The underfloor auger
must be level within 1/4” (6 mm) per 10’ (3048 mm) of span or not more than 1/2” (13 mm) for whole
underfloor auger. This will prolong life and ensure smooth operation.
4. Anchor the underfloor auger to the bin floor using concrete anchor bolts through the holes in the factory-
installed anchor legs. The anchor bolts are purchased separately according to type (see
).
a. Install two concrete anchor bolts in the anchor legs nearest the center sump.
b. Install the remaining concrete anchor bolts in the anchor legs at equal intervals along the remainder of
the underfloor auger.
5. Cut an opening in the bottom spacer sheet (refer to
Section 4.5 – Bin Wall Cutout on page 20
).
6. Slide the spacer sheet over top of the unload and re-attach to the bin door using the existing 3/8” x 1–1/2”
bolts and nuts.
Go to
Section 6.4 – Install the Bin Adapter on page 33
.
6.3.2 Install by Cutting a Bin Sheet in Place
This procedure describes cutting the opening for the underfloor auger with the sheet in place after the bin
sidewall has been anchored to the foundation. This procedure requires some disassembly and reassembly of
components in order to install the underfloor auger. This procedure is allowed for use with all bin
manufacturers and for any appropriate sidewall sheet at the bin bottom (under the door and elsewhere).
C
C
EASYFLOW2 (100 SERIES) – FARM TUBE BIN UNLOAD SYSTEM