There are two v-plow adjustment bolts on each side of the tail section. Loosen all
bolts, adjust v-plow, and tighten to set (Figure 5.23).
Figure 5.23
5.7. COVER INSTALLATION
The conveyor must be completely installed with all inlets/loaders in the proper
locations before installing covers.
5.7.1. M
ADE
-T
O
-L
ENGTH
C
OVERS
See Figure 5.24, 5.25, and 5.26.
Measure from the centerline of the channel flange to inlet flange as shown in
Figure 5.25. This is the measurement that is required by the factory to manufac-
turer made-to-length covers.
All of the covers that are going to be made-to-length must be measured using the
same procedure; the location of each of these covers should be noted.
These measurements need to be called in or sent to the Hi Roller engineering
department.
Figure 5.24