13
Commissioning
EN
ProCalida® IN 1½
6.2
Performing the pressure test and the function test
1. Apply 6 bar of pressure to the system for a period of two hours.
2. Perform a leak test after two hours.
- The pressure drop must not exceed 0.2 bar.
3. Fill the system with water until the operating pressure is reached.
6.3
Adjusting the flow valves
6.3.1
With flow meter
1. Open the flow valve until the cal-
culated water volume (A) is indi-
cated at the flow meter.
2. Turn the ring all the way to the
mechanical stop of the flow valve.
A
Summary of Contents for ProCalida IN 1 1/2
Page 11: ...11 Montage DE ProCalida IN 1 5 2 Produkt montieren Klick ...
Page 16: ...16 Gewährleistung DE ProCalida IN 1 ...
Page 27: ...11 Mounting EN ProCalida IN 1 5 2 Mounting the product Click ...
Page 32: ...16 Warranty EN ProCalida IN 1 ...
Page 43: ...11 Montage FR ProCalida IN 1 5 2 Montage du produit Clic ...
Page 48: ...16 Garantie FR ProCalida IN 1 ...
Page 59: ...11 Montaggio IT ProCalida IN 1 5 2 Montaggio del prodotto Clic ...
Page 64: ...16 Garanzia IT ProCalida IN 1 ...