25
Aermec cod. 6976420_03 15.03
Omnia UL_R/UL_RI 26-36
EN
5. PIPE
CONNECTIONS
5.1. HYDRAULIC
CONNECTIONS
Ensure the water piping, condensate drain and
electrical circuit are already installed.
The selection and sizing of the pipework is the
responsibility of the designer, which must be in
accordance with good practices and applicable
legislation.
Always use a counter-spanner when fixing pipe-
work with a spanner.
It is recommended that pipework is suitably
insulated to prevent condensation in cooling
mode, even if the Omnia UL_R and UL_RI have
a condensate drain tray as standard. Carry out a
leak test of all hydraulic connections.
SC
35
34
69
216
5.2. CONDENSATE
DRAIN
In cooling mode the unit removes humidity from
the internal air. This condensate must be re-
ŵŽǀĞĚďLJĐŽŶŶĞĐƟŶŐƚŚĞƵŶŝƚ͛ƐĐŽŶĚĞŶƐĂƚĞĚƌĂŝŶ
outlet to the condensate drain system.
Note:
ĞĨŽƌĞĐŽŶŶĞĐƟŶŐƚŚĞĐŽŶĚĞŶƐĂƚĞĚƌĂŝŶ͕ƉŝĞƌĐĞ
the diaphragm of the drain pan, on the hydrau-
ůŝĐĐŽŶŶĞĐƟŽŶƐƐŝĚĞ͕ǁŝƚŚĂƐƵŝƚĂďůĞƚŽŽů͘^ĞĂů
the drain hole not used.
Connect the drain pan discharge to the conden-
sate drain system with a drain tube. The drain
ƉĂŶĐŽŶŶĞĐƟŽŶŝƐŽŶůLJĚĞƐŝŐŶĞĚĨŽƌƵƐĞǁŝƚŚ
ŇĞdžŝďůĞƚƵďĞƐŽĨĂĚĞƋƵĂƚĞŝŶƚĞƌŶĂůĚŝĂŵĞƚĞƌ͘
Avoid imposing any loads and do not use for any
other purpose.
The condensate drain system must be adequately
sized and the piping arranged to ensure a suf-
ĮĐŝĞŶƚŝŶĐůŝŶĞĂůŽŶŐƚŚĞůĞŶŐƚŚ;ŵŝŶŝŵƵŵϭйͿ͘/Ĩ
connected to the sewerage system it is recom-
mended that a trap is used to prevent odours
rising into the space.
IN
Water inlet
OUT
Water outlet
SF
Air vent
SC
Water drain
Model OMNIA UL_R - UL_RI
26
36
Water flow rate
(l/h)
349
487
Coil water content
(l/h)
0.8
1.1
Coil connections (in/out)
(inch)
1/4”
1/4”
Condensate drain
Drain pan diaphragm for dis-
charge of the condensate drain
tZE/E'
Leak test the condensate drain.
tZE/E'
Only left hand pipe connections
are possible and the coil cannot
be reversed
.
INSTALLATION EXAMPLES
Radiant panel
By pass
AB
A
B
OUT
IN
Radiant panel
By pass
AB
A
B
OUT
IN
Coil