background image

 
 
 
 

 

Maschinenfabrik Reinhausen GmbH - AEG Compensation Systems | Sickingenstraße 71 | 10553 Berlin / Germany 

Phone : +49 30 34692-0 | Fax : +49 30 34692-255 | email: [email protected] | Internet: http://www.reinhausen.com

 

 

Operating & Commissioning Instructions BLR-CA 

 

 
 

As with all electrical equipment, the appropriate specifications governing electrical installation must be followed when Power Factor 
Correction Equipment is installed. When removing the front nameplate to adjust the function switch and DIP switches, always 
ensure that your body is not carrying any electrostatic charge. This can be accomplished by simply touching a grounded object, such 
as the switchboard metal casing to dissipate any electrical charge before removing the cover plate. 
 

1. Check that the Measurement and Control Voltage, Supply Frequency and Current Transformer rating comply with the ratings given on the 
back of the relay. 
 
2. Mount the relay in the switch panel. The cut out size is 138x138 mm. The relay is secured either 
a; with two fixing bolts 
b; with mountig parts for wall fastening – side mounting (optional). 
 
3. Connect up in accordance with the wiring diagram. 

Pay special attention to the cross section size of the C.T. connections. We 

recommend for runs up to 10 metres 2,5 mm

cross section. 

An integrated voltage observation in BLR-C.. guarantees a safety-disconnection of the capacitors in case of decreasing voltage below 70% 
AC. It is due to this device necessary to connect terminal "

A

" for control voltage to 

L2 

as shown in wiring diagram. This ensures a proper 

disconnection of the contactors. 
 
4. Check that transformer current setting at coding switch (

S1

) is correct - OFF = x/1A - ON = x/5A. 

 
5. Adjust DIP switch 

(S2)

 to select p.f. Alarm function ON (in circuit) or OFF (out of circuit). 

 
6. Apply the measurement and control voltages. Connect the Current Transformer, and remove any short circuit link. Indication "I --0": no 
current flowing, resp. <1% of nominal secondary c.t. current. Active steps are cut off automatically after 10 minutes. There is no cutoff if the 
system is operated manually. 
Any p.f. controlling starts, if reactive vector exceeds >1% of nominal secondary c.t. current at least. 
 
7. Function switch 

(3)

 in position 3 = automatic operation 

Required target p.f. = 1, switching time = 40s and step limitation are factory-preset. Wait for the 90 sec. lockout time to elapse. During this 
time the required parameters can be set as listed below, using the -/+ buttons (4/5). Each set value is stored in the memory, once the function 
switch is moved on to the next position. 
 
8. With function switch (3) in 

position 1

, select the required target p.f. using +/- buttons. 

 
9. With function switch (3) in 

position 2

, select the required switching step time delay, using +/- buttons. 

 
10. With function switch in 

position 5

, select the number of switching steps, using the +/- buttons. The relay is delivered with this setting on 

its maximum number of steps. If the max. number of steps is selected, but capacitors are not connected to all the steps, the relay will 
recognize this, and will make three switchings to verify there is no connection. The disconnected step(s) will then be excluded from the 
switching sequence process. With function switch in 

position 6

, the number of disconnected or defective steps will be shown. After 7 days, a 

system power failure, or deletion of the values with the function switch in position 6 (using +/- buttons>20s), the disconnected steps will be 
automatically reactivated and a renewed switching attempt will be made. 
 
11. 

Set function switch (3) in position 3, so that the installation is in "Automatic" operation.

 

 

12. The digital indicator will show the system power factor. 
f.e. 

iiii

0,87 for lagging or  

c

0.94 for leading load. 

 

13. After the lock out time, with an inductive load on the system, if the relay is correctly connected, the + LED will start to flash. 
 
14. If the installation is correctly connected, the relay will now switch successive steps, following the selected step time delay until the target 
power factor is obtained. Each energized step will be indicated on the LED display 

6

. As each step switches in, so the digital display of 

power factor will change. If the installation p.f. is above or below the target p.f., the "+" LED (Below Target) or "-" LED (Above Target) will 
flash. 
 

Summary of Contents for BLR-CA

Page 1: ...utoff if the system is operated manually Any p f controlling starts if reactive vector exceeds 1 of nominal secondary c t current at least 7 Function switch 3 in position 3 automatic operation Required target p f 1 switching time 40s and step limitation are factory preset Wait for the 90 sec lockout time to elapse During this time the required parameters can be set as listed below using the button...

Page 2: ... then this will be shown as an alarm in the display HA__ will flash at 5 second intervals e If both alarms are signalling together then the symbols AH__ will flash in the display f If external fault signalling contacts for power factor m are fitted the alarm contact is given between terminals M MR AL or AH g At CA regulators with external alarm contact option z or L contact via terminal M MZ will ...

Page 3: ...e data The stored data of all steps can be cancelled by depressing the buttons together for a period of 20 secs Automatic regulation is active during this time 8 Indicates the measured unit of value of each step which is proportional to the capacitor output in kVAr For example the display will show CC 12 for 2 secs to indicate step No 12 and will then alternate to 125 units of value Once the value...

Page 4: ...r m capacitor alarm message external z harmonic alarm external e single phase measurement NT 2nd cusp point see point A L Fan Control v BAL_CA_06 03_e CA12 Reverse voltage path at Connection diagram 01 03 fault signals Measurement 150 240 220 240 VAC N Power supply N L2 L3 L1 N L1 P VAC MR MZ M k l Spezial versions e z m 380 415 V C1 14 4 A L2 4 A L3 4 A A 1 2 3 4 5 6 7 CA06 8 9 Rotation Sense 10 ...

Reviews: