3 Installation
UPS IST7 (10KVA-40KVA)
User Manual
26
Transport the UPS to assigned site.
Unpack the external package, and take out the fittings.
Check the UPS.
Inspect the appearance and check if there has any damage caused by transportation. If
damaged, please inform the carrier immediately.
Compare with the packing list and check if the fittings are complete and proper. If the
fittings lack or model wrong, please take note and contact the local agency of our company.
Put the front plate down to become an oblique board.
After checking, unscrew the bolts that connected with the UPS and wooden bracket and the supporting
plate by socket wrench, remove the supporting plate.
Bolts position
The bolts position of IST7 series (10kVA-40kVA) is the same, above we take IST740 as an example to
illustrate.
Heighten the supporting feet.