4.1 UNIT WILL NOT START
A.
Power off. Check main disconnect.
B.
Main line open. Check fuses.
C.
Loose terminals. Tighten terminals with POWER OFF.
D.
Control circuit open. Check control voltage fuses and transformer.
4.2 COMPRESSOR HUMS BUT WILL NOT START
A.
Contactor problem. Check contacts and contactor operation.
B.
Low voltage. Check voltage at main and at the unit. If voltage is OK at the main but low
at the unit, increase wire size. If low at main, consult your local power company. Voltage
must be +/- 10% nameplate rating.
C.
No power on one phase of a three phase unit. Check fuses in control panel and main
disconnect. Also check unit wiring, main plant fuse and wiring. If the problem is with the
main power supply coming into the plant, call the local power company.
D.
Loose terminals. Power off and follow all company lock-out tag-out procedure before
tightening terminals.
4.3 SHUTS OFF ON HIGH PRESSURE LIMIT
Note: Units may be equipped with either an adjustable or non-adjustable
“fixed” high pressure switch. If the refrigerant pressure exceeds the
setting of the adjustable switch it must be manually reset when the
discharge pressure falls to a safe level. The non-adjustable “fixed”
high pressure switch will automatically reset when the discharge
pressure falls to a safe level.
A.
Air-cooled units:
1.
Insufficient condenser air flow. Check condenser filter for
dirt, fins may be plugged with dirt or foreign material. Also,
check for proper fan rotation.
Note: All enclosure panels on the air-cooled condenser
must be attached.
2.
Fan motor not operating. Have electrician check fuses and wiring, motor starter
and overloads, and motor. Repair or replace motor if defective.
Adjustable High
Pressure Switch
Fixed High
Pressure Switch
WARNING: Before troubleshooting or servicing this unit, follow all company lock-out tag-out
procedures.
Summary of Contents for Titan
Page 2: ......
Page 6: ...Page 6 THIS PAGE INTENTIONALLY BLANK ...
Page 24: ...Page 24 THIS PAGE INTENTIONALLY BLANK ...
Page 50: ...Page 50 THIS PAGE INTENTIONALLY BLANK ...
Page 58: ...Page 58 THIS PAGE INTENTIONALLY BLANK ...
Page 74: ...Page 74 THIS PAGE INTENTIONALLY BLANK ...
Page 94: ...END 2021 ADVANTAGE ENGINEERING INC RE 20210407 ...