Associated Documentation
•
Site plan or floor plan
•
Installation plan including details of the current electrical systems
•
Cabling plan for interconnecting the modules and shelves, if required
•
“Site Survey Checklist” on p. 85
)
Site Survey Checklist
This checklist is provided to ensure that your site meets all of the requirements.
The customer or installing technician is required to review the following checklist
prior to each installation. Please print out this list and check all appropriate
boxes.
Table 20: Site Survey Checklist
Site Information
Location/Node:
Address:
Responsible Person:
Phone/Cell Phone:
No.
Checks
Yes No
Remarks
Documents Required
1
Is a site plan or a floor plan available with all relevant
information about the racks, cutouts for cables etc.?
2
Is an installation and cabling plan available?
3
Is a sketch of the system configuration available?
Personal Safety Requirements
4
Is the installation location clean?
5
Are there possible hazards in the work area, such as
wet floors, unearthed or damaged power extension
cords, and missing safety grounds.
General Installation Location Requirements
6
Is the installation location in a limited access area,
powered on 24 hrs/day, 7 days/week?
7
Is the installation location permanently free from
excessive dust and moisture?
8
Are floor tile cutouts or ceiling ducts for cable access
available, and are they the right size?
9
Is there a telephone extension?
Equipment Rack Requirements
10
Is enough rack capacity available to accommodate all
shelves?
11
Is (are) the rack(s) stable enough to carry multiple fully
populated shelves?