Site Preparation
84
Installation and Commissioning Manual
F
S
P
3000R
7 R
11
.1 8000
0015930
Issue
B
, ©
2012
ADVA AG Optical Netw
orking
ADVA Conf
idential
•
Provide all fiber-optic patch cables with the appropriate connectors, route
the cables from the FSP 3000R7 system to the existing fiber-optic network
and label the cables.
•
Test and record individual line losses.
•
Install a separate PDU on the top of the rack and ensure that it supplies -48
V DC.
•
Install separate branch circuits with power receptacles of a three-conductor
earthing type to provide AC power (100/240 V AC, 60/50 Hz), if necessary.
•
Provide full-system online test jobs.
Ensure the site is ready for installation as stipulated in the contract. Use the
checklist in
“Site Survey Checklist” on p. 85
.
Checking the Site
Your site must comply with the requirements described above before you install
the FSP 3000R7. The main tasks to prepare for installation of the FSP 3000R7
equipment on an existing site are:
•
Checking documents required
•
Checking personal safety requirements
•
Checking general location requirements
•
Checking equipment rack requirements
•
Checking ventilation requirements
•
Checking clearance requirements
•
Checking environmental requirement
•
Checking power source requirements
•
Checking cable and cabling requirements
Do not begin installation until unacceptable conditions are corrected.
Specialized Knowledge Required
Checking power requirements and power cable requirements must be per-
formed by a qualified electrician.
Tools Required
•
Common measuring tools, such as a self-retracting pocket tape measure to
check space requirements
•
Multimeter to check power requirements
P
S
Note
The customer is responsible for ensuring that the site consistently
conforms to all requirements, and that necessary peripherals are
made available to ADVA Optical Networking Service personnel during
installation.