Installing the FSP 3000R7
ROADM-C40/40/OPM-3HU/2DC Shelf
This section describes how to install the ROADM-C40/40/OPM-3HU/2DC Shelf
in the equipment rack. Procedures for earthing the shelf, installing the power
cables and testing the earthing and DC power connections are also provided
along with relevant safety and equipment precautions.
This section contains the following subsections:
Rack Mounting the FSP 3000R7 ROADM-C40/40/OPM-3HU/2DC Shelf
Earthing the ROADM-C40/40/OPM-3HU/2DC Shelf
Testing the Earth and DC Power Connections
Rack Mounting the FSP 3000R7
ROADM-C40/40/OPM-3HU/2DC Shelf
The ROADM-C40/40/OPM-3HU/2DC shelf can be mounted into 19 and 23-inch
equipment racks. There are adapter brackets in the installation kit that are used
to mount the shelf into a 23-inch rack. Otherwise the unit is designed to fit a
standard 19 inch rack.
The adaptor brackets securing the shelf to the rack have two holes each.
General Considerations
When mounting ROADM-C40/40/OPM-3HU/2DC shelves into a rack, consider
the following:
•
Follow the guidelines for installing shelves as called out in this
•
Mount ROADM-C40/40/OPM-3HU/2DC shelves according to your installa-
tion plan.
•
If you are installing the shelf in a rack, make sure that both sides of the shelf
are accessible for power terminal block installation, or connect the power
terminal cables before you mount the shelf.
The topmost FSP 3000R7 shelf is typically the master shelf. The
ROADM-C40/40/OPM-3HU/2DC shelves are usually mounted below the FSP
3000R7 shelf. Where the shelves are mounted in the rack is not mandatory.
They can be mounted in any position in the rack. Refer to your cabling plan. For
a typical example of how the ROADM-C40/40/OPM-3HU/2DC shelves are
mounted, see
.