Figure 8:
Attached ESD Connection Adaptor
Step 13 If no other installation work follows, reattach the front cover by press-
ing the outer black latches and releasing it onto the corresponding fix-
ing brackets (see
End of Procedure
Fitting the 9HU, 7HU Shelves and 1HU Equipment
Shelves with ETSI or NEBS Brackets
The FSP 3000R7
9HU shelf, 7HU shelf types and 1HU equipment shelf types
can be mounted to open racks or into customer cabinets of the specified stan-
dard widths: 19 inch, 21 inch and 23 inch. They also fit into a 300 mm (0.984 ft.)
deep ETSI rack.
The 9HU shelf, 7HU shelf types and 1HU equipment shelf types come
pre-installed with 19-inch brackets. If a shelf is to be mounted to an ETSI or
NEBS compliant rack, you must remove the 19-inch brackets and fit the appro-
priate adaptor bracket pair.
The ETSI, NEBS and 19-inch brackets are fitted on the outside of the left- and
right-hand side walls.The ETSI and NEBS brackets are delivered with the 9HU
shelf, 7HU shelf and 1HU Equipment Shelves.
ESD Connection
Adaptor
Front-Cover
Fixing Bracket
19-Inch
Bracket
Threaded Holes for
Another Potential
Location of the
ESD Adaptor