Installation, Commissioning and Maintenance 

Installation 

The ground shall be strong enough to back up 

load. 

Batteries integrated in equipment should be 

compliance with the installation instructions, 

separately installed on rack and cabinets should 

be connected by bolts to the foundation. 

Battery racks or cabinets should be properly 

installed according to instructions. 

Connecting 

Before connecting, make a overall check of all 

the batteries and connectors to see whether 

there is hardware damage or manufacturing 

defects in order to guarantee the polarity are 

correct. 

The charge equipments are in cut-off state and 

without loads, then connect the positive and 

negative terminals to chargers. 

During the installation and transit of the battery, 

use insulted tools, gloves, aprons and safety 

glasses; do not touch connecting terminals and 

safety valve in transit. 

Placing tools and conductive articles on the 

battery is strictly prohibited. 

Maintain the connecting terminals clean and 

tighten the connectors as per required torque 

value. 

Commissioning 

Assure battery operation in the clean 

environment; 

At 20

, charge the battery with 2.24Vpc for 16 to 

24 hours, or with 2.35Vpc for 8 to 12 hours; 

charge voltage should be adjusted according to 

the ambient temperature. 

Maintenance 

Monthly maintenance: 

  Measure and record the ambient temperature 

of the battery room, battery container and 

terminals. 

  Check container, lid and terminal surface 

defects and temperature of each battery. 

  Measure and record the total voltage and 

floating current of the battery system. 

  Correct problems once found. 

Quarterly Maintenance: 

  Repeat every item of monthly inspection. 

  Measure and record floating voltage of every 

on-line battery. 

Annually Maintenance: 

  Repeat quarterly maintenance and inspection. 

  Check whether the connectors are loose or 

not. 

  Check whether the safety valve is tight or not. 

  Perform a discharge test to check the exact 

load every year and discharge 30~40% of the 

rated capacity. 

Three-year Maintenance: 

  Carry out a capacity test(C

10

) every three 

years and every year after six years' of 

operation. If the capacity of the battery is lower 

than 60% of the rated capacity, the battery 

should be replaced. 

Security Instruction 

  Only professionals shall be allowed to open 

and maintain the battery with insulated tools; 

Any metal objects to be put on top of the 

battery shall be strictly prohibited; 

  The battery should be stored and installed 

upright; upright down or on one side is 

prohibited; 

  Please do not use any organic solvent to clean 

batteries; 

  Please do not smoke or set out fire near 

batteries; 

  Please do not remove the relief valve or put 

anything into the battery; 

  Please charge the battery within 24 hour after 

the discharge; 

  Long storage time would result the 

degeneration of battery performance, and 

suggest use the battery early. 

 

 

 

 

 

14

 

Summary of Contents for GFMJ Series

Page 1: ......

Page 2: ...es 01 3 Applications 02 4 Standards 02 5 Certification 02 6 Battery construction 02 7 General Specifications 04 8 Technology 05 9 Performance Data 06 10 Operating instruction and Guidelines 12 11 Inst...

Page 3: ...long cyclic life Patented relief valve Multi fold vent system comprised of proprietary gel specialized low pressure safety valve with acid filtering and flash arrester minimizes bulging and prevents...

Page 4: ...d vibration resistant prevents leakage and container deformation Applications Telecommunication base station exchange station Dedicated telecommunication station for power system military station Data...

Page 5: ...GFMJ 200 and GFMJ 300 GFMJ 400 500 600 GFMJ 800 and GFMJ 1000 GFMJ 1200 GFMJ 1500 and GFMJ 2000 03...

Page 6: ...FMJ 150 12 150 188 513 232 218 228 63 8 560 1600 3 65 M8 16 D 6GFMJ 200 12 200 250 513 296 5 218 228 82 8 660 1850 3 20 M8 16 D GFMJ 200 2 200 250 171 107 334 344 14 8 800 1900 0 68 M8 18 F GFMJ 300 2...

Page 7: ...cium alloy which inhibit the hydrogen evolution The batteries apply special gel electrolyte technology and the gel is with three dimensional net porous structures and also with some tiny cracks as gas...

Page 8: ...49 1 38 2 29 2 22 30 14 90 8 50 4 59 3 93 2 07 1 06 0 93 0 49 1 65 225 167 132 111 82 64 48 2 37 7 29 2 22 30 14 90 8 50 4 59 3 93 2 07 1 06 0 93 0 49 1 70 212 158 130 109 81 62 48 2 37 1 29 2 22 30...

Page 9: ...81 6 55 65 48 30 38 70 31 95 16 65 14 05 7 29 3 75 3 27 1 74 1 75 450 419 372 329 276 182 108 5 80 4 54 6 47 55 37 95 31 35 16 50 13 90 7 29 3 75 3 27 1 74 1 80 420 398 344 303 255 168 104 1 76 8 52...

Page 10: ...204 00 159 60 135 00 67 80 57 50 29 16 15 00 13 08 6 96 1 70 1920 1770 1560 1362 1140 738 442 2 326 4 222 6 193 20 154 80 127 80 66 60 57 30 29 16 15 00 13 08 6 96 1 75 1800 1674 1488 1314 1104 726 43...

Page 11: ...5 95 3 16 1 63 1 43 0 76 1 75 251 203 173 147 113 85 67 52 5 42 3 30 60 20 90 12 10 6 60 5 95 3 16 1 63 1 43 0 76 1 80 234 185 165 138 108 82 66 0 51 3 41 2 29 80 19 80 11 80 6 40 5 72 3 16 1 63 1 43...

Page 12: ...9 104 71 48 60 38 50 31 90 18 30 16 70 9 72 5 00 4 40 2 34 1 75 547 515 462 410 346 229 138 103 70 46 90 37 20 30 70 18 30 16 50 9 72 5 00 4 40 2 34 1 80 523 498 434 383 325 214 135 99 68 45 20 35 80...

Page 13: ...70 1915 1625 1070 675 495 340 226 00 179 00 150 00 80 50 91 50 48 60 25 00 22 00 11 70 1 85 2290 2195 2010 1830 1545 1055 640 0 470 0 325 0 215 00 171 00 142 00 76 50 88 00 48 60 25 00 22 00 11 70 GFM...

Page 14: ...2 30 2 21 35 2 19 3 2 The batteries need an equalization charge or supplemental charge in the following conditions Supplemental charge battery after the installation of battery system and before the o...

Page 15: ...o constant voltage h Constant voltage V cell Charging time h 20 0 1C10 1 6 2 35 8 0 15C10 1 2 2 35 6 50 0 1C10 4 3 2 35 14 0 15C10 3 3 2 35 12 80 0 1C10 6 8 2 35 16 0 15C10 5 5 2 35 14 100 0 1C10 8 7...

Page 16: ...rd the ambient temperature of the battery room battery container and terminals Check container lid and terminal surface defects and temperature of each battery Measure and record the total voltage and...

Page 17: ...th Master distributors and Country managers who apply ABT commercial strategy and through Global Key Account in Advanced Battery Technology BV Add New Yorkstraat 14 1175 RD Lijnden Amsterdam Netherlan...

Reviews: