Section 7
Checking installation
7.1
Identifying hardware and software version
GUID-7527A986-F827-4104-B0E9-C62B1B0EF706 v1
The information of hardware and software versions of the IED are available on the
label attached on the case of the IED. There are also module labels that can be used
to identify the different modules inside the IED (such as input-output cards and so
on).
7.2
Checking mounting
GUID-50578D7B-23D4-45B0-BB10-D3108EEF9B97 v2
Check that all fixing screws are tight and that all cables are connected.
7.3
Checking the power supply
M11725-2 v6
Do not insert anything else to the female connector but the
corresponding male connector. Inserting anything else (such as a
measurement probe) may damage the female connector and prevent
a proper electrical contact between the printed circuit board and the
external wiring connected to the screw terminal block.
Check that the auxiliary supply voltage remains within the permissible input
voltage range under all operating conditions. Check that the polarity is correct
before energizing the IED.
7.4
Energizing the IED
GUID-E40DE80C-8DA4-4E17-876C-4CC3CE706347 v3
Before connecting the auxiliary power, check that the terminal strip is wired and
placed correctly. Remove the protective film from the top side of the unit.
During IED start-up, you can observe the following sequence:
1. The Green Ready LED starts to flash.
2. The LCD lights up and
starting...
is displayed.
3. The main menu is displayed. A final steady green Ready LED indicates a
successful start-up of the device.
1MRK 514 026-UEN B
Section 7
Checking installation
670 series 2.2 IEC
83
Installation manual
Summary of Contents for Relion 670 series
Page 1: ...RELION 670 SERIES 670 series Version 2 2 IEC Installation manual ...
Page 2: ......
Page 10: ...4 ...
Page 18: ...12 ...
Page 24: ...18 ...
Page 88: ...82 ...
Page 100: ...94 ...
Page 110: ...104 ...
Page 111: ...105 ...