. Compare the result of the measurement
with the set value.
3.
to
to find the operating value for test points 2, 3 in table
Observe that the zones that are not tested have to be blocked and the zone that
is tested has to be released.
4.
to
to find the operating value for the phase-to-earth fault L3-
E according to figure
and table
.
Test points 8, 9, 10 and 11 are intended to test the directional
lines of impedance protection. Since directionality is a
common function for all six measuring zones, it is only
necessary to test points 8, 9, 10 and 11 once, in the forward
direction in order to test the accuracy of directionality
(directional angles). Directional functionality testing (trip
inside, no-trip outside) should always be made for all
impedance zones set with directionality (forward or reverse).
11.4.8.2
Measuring the operating time of distance protection zones
GUID-70AEC42A-9BC7-445A-AE21-2CEC0C3A79DC v3
Procedure:
1.
Subject the IED to healthy normal load conditions for at least two seconds.
2.
Apply the fault condition to find the operating time for the phase-to-phase
fault according to test point 10 in figure
and table
for zone 1. Compare
the result of the measurement with the setting
t1PP
.
3.
to
to find the operating time for the phase-to-earth fault
according to test point 10 in figure
measurement with the setting
t1PE
.
4.
to
to find the operating time for all other used measuring
zones.
Observe that the zones that are not tested have to be blocked and the zone that
is tested has to be released.
11.4.8.3
Completing the test
GUID-7FA2EA27-B6E2-48AB-8D53-22425E322FFA v1
Continue to test another function or end the test by changing the
TESTMODE
setting to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.4.9
Power swing detection ZMRPSB
M13888-2 v9
The aim is to verify that the settings of the Power swing detection function
ZMRPSB is according to the setting table and to verify that ZMRPSB operates as
expected.
Section 11
1MRK 505 378-UEN A
Testing functionality by secondary injection
140
Line differential protection RED670 2.2 IEC
Commissioning manual
Summary of Contents for RED670 Relion 670 series
Page 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Page 2: ......
Page 18: ...12 ...
Page 36: ...30 ...
Page 68: ...62 ...
Page 72: ...66 ...
Page 108: ...102 ...
Page 278: ...272 ...
Page 282: ...276 ...
Page 288: ...282 ...
Page 306: ...300 ...
Page 307: ...301 ...