Start-up
Contents of this chapter
This chapter provides instructions for start-up of the PVS800-IS inverter station.
WARNING!
Only an authorized electrician is allowed to install, start up and maintain the inverter
station. Follow the
and the local safety regulations.
If ignored, physical injury or death may follow, or damage may occur to the
equipment.
Tools needed
•
Computer with the Drive composer PC tool installed (for the inverter diagnostics and
settings)
•
Multimeter
Start-up tasks
Note:
These instructions are valid for a typical system (solar plant, inverter station and MV
substation) such as the one presented in the example
Main circuit diagram (page 17)
. The
symbols in square brackets, for example [U1], refer to the device designations used in the
circuit diagrams.
Additional information
Task
Pre-checking the switchgear (voltage not connected)
See the switchgear manufacturer’s instructions.
8
Start-up 41