3.3 On-site installation
3.3.1 Brief installation procedure
Introduction
This procedure is a brief guide when installing the robot for the first time. Also see
Pre-installation procedure on page 52
.
First installation
Use these procedures to install the IRB 6730.
Note
Action
Transport the manipulator to its intended location.
1
See
.
Install the valid platform or prepare the foundation
for the manipulator.
2
See
Lift and secure the manipulator to the plat-
form/foundation.
3
See
Orienting and securing the ro-
See
•
Product manual - OmniCore
V250XT Type A
Connect the manipulator to the controller.
4
See
•
Product manual - OmniCore
V250XT Type A
Configure the safety settings.
5
See
•
Product manual - OmniCore
V250XT Type A
How to start and run the robot is described in the
product manual for the controller.
6
Install required equipment, if any.
7
DANGER
Make sure all safety requirements are met when
performing the first test run. See
installation, maintenance, or repair on page 96
.
8
Product manual - IRB 6730
55
3HAC085699-001 Revision: B
© Copyright 2023 ABB. All rights reserved.
3 Installation and commissioning
3.3.1 Brief installation procedure
Summary of Contents for IRB 6730
Page 1: ...ROBOTICS Product manual IRB 6730 ...
Page 8: ...This page is intentionally left blank ...
Page 14: ...This page is intentionally left blank ...
Page 36: ...This page is intentionally left blank ...
Page 50: ...This page is intentionally left blank ...
Page 176: ...This page is intentionally left blank ...
Page 604: ...This page is intentionally left blank ...
Page 628: ...This page is intentionally left blank ...
Page 634: ...This page is intentionally left blank ...
Page 659: ......