2 Installation and commissioning
2.4.1. Pre-installation procedure
47
3HAC026876-001 Revision: C
© Copyri
ght
200
6-2008 ABB.
All rights reserved.
2.4 Unpacking
2.4.1. Pre-installation procedure
General
This section is intended for use when unpacking and installing the robot for the first time. It
also contains information useful during later re-installation of the robot.
Checking the pre-requisites for installation
The checklist below details what must be observed before proceeding with the actual
installation of the robot:
Weight, robot
The table below shows the weights of the different models:
* Weight of robot excluding DressPack.
Action
1. Make sure only qualified installation personnel conforming to all national and local
codes are allowed to perform the installation.
2. Visually inspect the robot to make sure it is not damaged.
3. Make sure the lifting device used is suitable to handle the weight of the robot as
specified in
.
4. If the robot is not installed directly, it must be stored as described in
5. Make sure the expected operating environment of the robot conforms to the specifica-
tions as described in
Operating conditions, robot on page 48
6. Before taking the robot to its installation site, make sure the site conforms to
,
Requirements, foundation on page 48
and
7. Before moving the robot, please observe
Risk of tipping / stability on page 53
regarding
risk of tipping!
8. When these prerequisites are met, the robot may be taken to its installation site as
described in section:
On-site installation
.
Robot model
Weight
IRB 6640 -180/2.55
1300 kg *
IRB 6640 - 235/2.55
1310 kg *
IRB 6640 - 205/2.75
1320 kg *
IRB 6640 - 185/2.8
1320 kg *
IRB 6640 - 130/3.2
1340 kg *
IRB 6640ID - 200/2.55
1395 kg *
IRB 6640ID - 170/2.75
1405 kg *
Continues on next page