Operation Manual / A130-H.. - A140-H..
9 Dismantling and fitting / 9.18 Installing the gas outlet flange
© Copyright 2021 ABB. All rights reserved.
HZTL4030_EN
Rev.G
July 2021
9.18
Installing the gas outlet flange
Fig. 57: Installing the gas outlet flange
1. If present: Insert the metal C-ring (57003) into the turbine casing (51000) and secure with
high-vacuum grease.
2. Install the gas outlet flange (57002) in the turbine casing.
3. Measure radial clearance (R) (see chapter Radial clearances N and R).
9.19
Installing the gas outlet casing
Fig. 58: Installing the gas outlet casing
Product
Size
Tightening torque [Nm]
A130
M8
20
A135
M10
40
A140
M12
65
Table 44: Tightening torque (51009)
1. Insert a new gasket (61002) into the gas outlet casing (61001).
2. Coat the threads of the studs (51008) with high-temperature grease.
3. Attach the lifting gear to the gas outlet casing (61001) and position the gas outlet casing
in the correct position on the turbine casing (51000).
Page
102
/
122
Summary of Contents for HT608827
Page 2: ......