30 Standard Commissioning Process
13. Reverse all disconnections and remove the short circuit wires.
Overview of high voltage part short circuit wiring
You can also measure the insulation resistance of the transformer separately from the
drive. Please see
.
Motor Insulation Test
The frame and the windings not being tested must be grounded during the insulation
resistance measurement.
All resistance temperature detectors (RTD) must be grounded.
The insulation resistance of a new motor is normally very high. A rule of a thumb can be
that if the measured value is one decade or more lower than the value measured in the
factory, check the winding for excess moisture or dirt. The test report contains the
insulation resistance value measured in the factory.
NOTICE
A short-circuit in any part of the drive will lead to severe damage.
Therefore, check that all short-circuit leads have been removed before energizing the
drive.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...