22 Standard Commissioning Process
Motor
•
Motor is installed, aligned and alignment protocol is available.
•
Motor is not coupled to the driven load.
•
Grounding is completed in compliance with local regulation.
•
Motor auxiliaries (bearing lubrication, heater cooling etc.) are ready.
•
Control and monitoring signals are connected. If this option is available.
•
Customer side motor protection set and ready. (e.g. winding temperature, vibration)
•
The user manual and technical specification is available.
•
Insulation of the motor has been tested according to manufacturing specifications. The
official test report must be available.
Power
•
Medium voltage is available for start-up of the converter.
•
Low voltage auxiliary power is available for start-up of the converter.
•
Low voltage space heater power is available. If this option is available.
Miscellaneous
•
Sufficient number and correct type of spare parts are available.
•
Desk and chair used for commissioning is available. Office power terminal is available.
•
The infrastructure of the electric room is finished and the installation site is sufficiently
ventilated or cooled and dehumidification to ensure the converter can running at the
appropriate temperature and humidity.
•
If operation with open doors filter of the room is available.
It is not allowed to operate with open door or windows of the electrical room if air is not
filtered.
•
Air conditioning or ventilating duct of the drive room is ready for load run of the
converter. Regarding last two options, window of electrical room should be with filter.
•
Air condition
•
Nature air cooling
•
Ventilating duct
Inspection of installation
In order to achieve a trouble-free commissioning, it is mandatory that the installation,
including third-party equipment, is inspected upon arrival.
The status of the installation is checked and it is verified that converter and related
equipment meet the applications specification. It should be verified that the installation is
done according to the installation instructions and the applicable safety regulations have
been met.
Check the installation with the guidance of the DriveStartup tool and the above Pre-
Commissioning Check Lists in
Checking the pre-conditions for commissioning
about installed equipment which is required by the report must be obtained and noted in
the corresponding sections of the report.
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...