Maintenance
After the operation of the circuit is validated at start-up, the STO function shall
be maintained by periodic proof testing. In high demand mode of operation, the
maximum proof test interval is 20 years. In low demand mode of operation, the
maximum proof test interval is 10 years; see section
. It is
assumed that all dangerous failures of the STO circuit are detected by the proof
test. To perform the proof test, do the
Validation test procedure (page 170)
Note: See also the Recommendation of Use CNB/M/11.050 (published by the
European co-ordination of Notified Bodies) concerning dual-channel safety-related
systems with electromechanical outputs:
•
When the safety integrity requirement for the safety function is SIL 3 or PL e
(cat. 3 or 4), the proof test for the function must be performed at least every
month.
•
When the safety integrity requirement for the safety function is SIL 2 (HFT =
1) or PL d (cat. 3), the proof test for the function must be performed at least
every 12 months.
The STO function of the drive does not contain any electromechanical components.
In addition to proof testing, it is a good practice to check the operation of the
function when other maintenance procedures are carried out on the machinery.
Include the Safe torque off operation test described above in the routine
maintenance program of the machinery that the drive runs.
If any wiring or component change is needed after start-up, or the parameters are
restored, do the test given in section
Validation test procedure (page 170)
Use only spare parts approved by ABB.
Record all maintenance and proof test activities in the machine logbook.
■
Competence
The maintenance and proof test activities of the safety function must be carried
out by a competent person with adequate expertise and knowledge of the safety
function as well as functional safety, as required by IEC 61508-1 clause 6.
174 The Safe torque off function
Summary of Contents for ACS180-04S-03A7-1
Page 1: ...ABB MACHINERY DRIVES ACS180 drives Hardware manual...
Page 2: ......
Page 4: ......
Page 12: ...12...
Page 24: ...24...
Page 84: ...84...
Page 96: ...96...
Page 146: ...146...
Page 148: ...Frame R0 148 Dimension drawings...
Page 149: ...Frame R1 Dimension drawings 149...
Page 151: ...Frame R3 Dimension drawings 151...
Page 152: ...Frame R4 152 Dimension drawings...
Page 160: ...160...
Page 180: ...Declarations of conformity 180 The Safe torque off function...
Page 181: ...The Safe torque off function 181...
Page 182: ...182 The Safe torque off function...
Page 183: ...The Safe torque off function 183...
Page 184: ...184...
Page 187: ...Installation 1 2 N m M4x16 2x 3 3 3 2 2 2 2 Accessories 187...
Page 189: ...Installation 3 3 2 2 2 3 2 2 N m M4x16 4x 1 Accessories 189...